Liv Maritime construction progress
The registered completion date for Liv Maritime in Dubai Maritime City is December 2028. At the last site inspection, in October 2026, it was 28% built. The developer is L I V Maritime Real Estate Development.
28%
Built, at the site inspection of 7 October 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- July 2029
- Construction started
- November 2024
- First registered
- January 2025
- Developer
- L I V Maritime Real Estate Development
- Community
- Dubai Maritime City
- Units
- 258
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- ليف ماريتايم
- Project number
- 3391
- Site inspections
- 5
Schedule
Between February 2026 and October 2026 the site added about 2.1 points a month. At that rate it would finish around July 2029, more than three months after its registered date of December 2028.
Site inspections
7 October 2026
28%+9.4 pts
19 May 2026
19%+7.7 pts
4 February 2026
11%+6.6 pts
23 July 2025
4.4%+4.4 pts
13 November 2024
0%
Context
Dubai Maritime City has 23 projects under construction, 32% built on average.
Own a unit in Liv Maritime?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Liv Maritime handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Liv Maritime?
- Liv Maritime was 28% built at the site inspection on 7 October 2026. The site has been inspected 5 times since November 2024. The Land Department took 30 site photos at its inspections.
- Is Liv Maritime delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Liv Maritime?
- The registered developer is L I V Maritime Real Estate Development.
- Which bank holds the escrow account for Liv Maritime?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Harbour LightsNearby in Dubai Maritime City. 72%, Due May 2027.
- Mar CasaNearby in Dubai Maritime City. 67%, Due October 2026, passed.
- Aria By BeyondNearby in Dubai Maritime City. 85%, Due January 2026, passed.
- Coral ReefNearby in Dubai Maritime City. 33%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.