Harbour Lights construction photos

59 photos from 10 site inspections, newest first. The percentage is how much of Harbour Lights was built on the day of each visit.

20 November 202672% built

9 July 202664% built

17 March 202653% built

19 November 202536% built

7 July 202526% built

21 January 202518% built

5 July 20248.4% built

30 November 20234.2% built

20 July 20232.0% built

21 November 20220% built

Back to Harbour Lights construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.