Ellington House IV construction photos
67 photos from 8 site inspections, newest first. The percentage is how much of Ellington House IV was built on the day of each visit.
22 July 202670% built
26 March 202650% built
10 December 202545% built
4 July 202538% built
29 January 202525% built
26 July 202411% built
4 April 20243.8% built
3 October 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)





















%2520-Elevation%2520(1).jpg&w=3840&q=75)
-%2520Level-6%2520(13).jpg&w=3840&q=75)
%2520-Elevation%2520(1).jpg&w=3840&q=75)
-Level-2%2520(2).jpg&w=3840&q=75)
-Level-G%2520(15).jpg&w=3840&q=75)
-%2520Level-6%2520(20).jpg&w=3840&q=75)
%2520-Elevation%2520(5).jpg&w=3840&q=75)
%2520-Level-8%2520(5).jpg&w=3840&q=75)
-Level-2%2520(24).jpg&w=3840&q=75)
%2520-Elevation%2520(3).jpg&w=3840&q=75)