Ellington House III construction progress

The register lists Ellington House III in Dubai Hills Estate as complete, with a registered completion date of July 2025. Its last site inspection on record was in July 2026. The developer is Eh 3 Development.

100%

Built, at the site inspection of 30 July 2026

Construction complete

Registered completion date
July 2025
Construction started
February 2023
First registered
April 2023
Developer
Eh 3 Development
Units
110
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
Iii إلينغتون هاوس
Project number
2581
Site inspections
10

Schedule

The register lists Ellington House III as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 July 2026

100%+5.0 pts

  • Ellington House III construction site, inspection photo 1, 30 July 2026
  • Ellington House III construction site, inspection photo 2, 30 July 2026
  • Ellington House III construction site, inspection photo 3, 30 July 2026
  • Ellington House III construction site, inspection photo 4, 30 July 2026

24 April 2026

95%+13 pts

  • Ellington House III construction site, inspection photo 1, 24 April 2026
  • Ellington House III construction site, inspection photo 2, 24 April 2026
  • Ellington House III construction site, inspection photo 3, 24 April 2026
  • Ellington House III construction site, inspection photo 4, 24 April 2026

24 December 2025

82%+9.7 pts

  • Ellington House III construction site, inspection photo 1, 24 December 2025
  • Ellington House III construction site, inspection photo 2, 24 December 2025
  • Ellington House III construction site, inspection photo 3, 24 December 2025
  • Ellington House III construction site, inspection photo 4, 24 December 2025

2 September 2025

72%+20 pts

  • Ellington House III construction site, inspection photo 1, 2 September 2025
  • Ellington House III construction site, inspection photo 2, 2 September 2025
  • Ellington House III construction site, inspection photo 3, 2 September 2025
  • Ellington House III construction site, inspection photo 4, 2 September 2025

9 April 2025

52%+20 pts

  • Ellington House III construction site, inspection photo 1, 9 April 2025
  • Ellington House III construction site, inspection photo 2, 9 April 2025
  • Ellington House III construction site, inspection photo 3, 9 April 2025
  • Ellington House III construction site, inspection photo 4, 9 April 2025

20 November 2024

32%+8.1 pts

  • Ellington House III construction site, inspection photo 1, 20 November 2024
  • Ellington House III construction site, inspection photo 2, 20 November 2024
  • Ellington House III construction site, inspection photo 3, 20 November 2024
  • Ellington House III construction site, inspection photo 4, 20 November 2024

4 July 2024

24%+12 pts

  • Ellington House III construction site, inspection photo 1, 4 July 2024
  • Ellington House III construction site, inspection photo 2, 4 July 2024
  • Ellington House III construction site, inspection photo 3, 4 July 2024
  • Ellington House III construction site, inspection photo 4, 4 July 2024

8 April 2024

12%+9.8 pts

  • Ellington House III construction site, inspection photo 1, 8 April 2024
  • Ellington House III construction site, inspection photo 2, 8 April 2024
  • Ellington House III construction site, inspection photo 3, 8 April 2024
  • Ellington House III construction site, inspection photo 4, 8 April 2024

30 October 2023

2.0%+2.0 pts

  • Ellington House III construction site, inspection photo 1, 30 October 2023
  • Ellington House III construction site, inspection photo 2, 30 October 2023
  • Ellington House III construction site, inspection photo 3, 30 October 2023
  • Ellington House III construction site, inspection photo 4, 30 October 2023

20 February 2023

0%

  • Ellington House III construction site, inspection photo 1, 20 February 2023
  • Ellington House III construction site, inspection photo 2, 20 February 2023
  • Ellington House III construction site, inspection photo 3, 20 February 2023
  • Ellington House III construction site, inspection photo 4, 20 February 2023

All 82 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Own a unit in Ellington House III?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Ellington House III handover date?
Construction of Ellington House III is recorded as complete, with a registered completion date of July 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Ellington House III?
Ellington House III was 100% built at the site inspection on 30 July 2026. The site has been inspected 10 times since February 2023. The Land Department took 82 site photos at its inspections.
Is Ellington House III delayed?
The register lists construction as complete.
Who is building Ellington House III?
The registered developer is Eh 3 Development.
Which bank holds the escrow account for Ellington House III?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.