399 Hills Park B construction progress

The register lists 399 Hills Park B in Dubai Hills Estate as complete, with a registered completion date of October 2025. Its last site inspection on record was in July 2026. The developer is National Properties.

100%

Built, at the site inspection of 31 July 2026

Construction complete

Registered completion date
October 2025
Construction started
February 2023
First registered
February 2023
Developer
National Properties
Units
199
Escrow bank
Dubai Islamic Bank
Name in Arabic
399 هيلز بارك ب
Project number
2510
Site inspections
9

Schedule

The register lists 399 Hills Park B as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 July 2026

100%+4.3 pts

  • 399 Hills Park B construction site, inspection photo 1, 31 July 2026
  • 399 Hills Park B construction site, inspection photo 2, 31 July 2026
  • 399 Hills Park B construction site, inspection photo 3, 31 July 2026
  • 399 Hills Park B construction site, inspection photo 4, 31 July 2026

15 April 2026

96%+5.2 pts

  • 399 Hills Park B construction site, inspection photo 1, 15 April 2026
  • 399 Hills Park B construction site, inspection photo 2, 15 April 2026
  • 399 Hills Park B construction site, inspection photo 3, 15 April 2026
  • 399 Hills Park B construction site, inspection photo 4, 15 April 2026

11 December 2025

90%+16 pts

  • 399 Hills Park B construction site, inspection photo 1, 11 December 2025
  • 399 Hills Park B construction site, inspection photo 2, 11 December 2025
  • 399 Hills Park B construction site, inspection photo 3, 11 December 2025
  • 399 Hills Park B construction site, inspection photo 4, 11 December 2025

2 September 2025

75%+8.1 pts

  • 399 Hills Park B construction site, inspection photo 1, 2 September 2025
  • 399 Hills Park B construction site, inspection photo 2, 2 September 2025
  • 399 Hills Park B construction site, inspection photo 3, 2 September 2025
  • 399 Hills Park B construction site, inspection photo 4, 2 September 2025

12 May 2025

67%+17 pts

  • 399 Hills Park B construction site, inspection photo 1, 12 May 2025
  • 399 Hills Park B construction site, inspection photo 2, 12 May 2025
  • 399 Hills Park B construction site, inspection photo 3, 12 May 2025
  • 399 Hills Park B construction site, inspection photo 4, 12 May 2025

17 December 2024

50%+16 pts

  • 399 Hills Park B construction site, inspection photo 1, 17 December 2024
  • 399 Hills Park B construction site, inspection photo 2, 17 December 2024
  • 399 Hills Park B construction site, inspection photo 3, 17 December 2024
  • 399 Hills Park B construction site, inspection photo 4, 17 December 2024

9 September 2024

34%+24 pts

  • 399 Hills Park B construction site, inspection photo 1, 9 September 2024
  • 399 Hills Park B construction site, inspection photo 2, 9 September 2024
  • 399 Hills Park B construction site, inspection photo 3, 9 September 2024
  • 399 Hills Park B construction site, inspection photo 4, 9 September 2024

4 January 2024

9.9%+9.9 pts

  • 399 Hills Park B construction site, inspection photo 1, 4 January 2024
  • 399 Hills Park B construction site, inspection photo 2, 4 January 2024
  • 399 Hills Park B construction site, inspection photo 3, 4 January 2024
  • 399 Hills Park B construction site, inspection photo 4, 4 January 2024

23 November 2022

0%

  • 399 Hills Park B construction site, inspection photo 1, 23 November 2022
  • 399 Hills Park B construction site, inspection photo 2, 23 November 2022
  • 399 Hills Park B construction site, inspection photo 3, 23 November 2022

All 84 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

National Properties has 1 project under construction in Dubai; 1 has passed its registered completion date.

Own a unit in 399 Hills Park B?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the 399 Hills Park B handover date?
Construction of 399 Hills Park B is recorded as complete, with a registered completion date of October 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on 399 Hills Park B?
399 Hills Park B was 100% built at the site inspection on 31 July 2026. The site has been inspected 9 times since November 2022. The Land Department took 84 site photos at its inspections.
Is 399 Hills Park B delayed?
The register lists construction as complete.
Who is building 399 Hills Park B?
The registered developer is National Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for 399 Hills Park B?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.