399 Hills Park B construction progress
The register lists 399 Hills Park B in Dubai Hills Estate as complete, with a registered completion date of October 2025. Its last site inspection on record was in July 2026. The developer is National Properties.
100%
Built, at the site inspection of 31 July 2026
Construction complete
- Registered completion date
- October 2025
- Construction started
- February 2023
- First registered
- February 2023
- Developer
- National Properties
- Community
- Dubai Hills Estate
- Units
- 199
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- 399 هيلز بارك ب
- Project number
- 2510
- Site inspections
- 9
Schedule
The register lists 399 Hills Park B as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
31 July 2026
100%+4.3 pts
15 April 2026
96%+5.2 pts
11 December 2025
90%+16 pts
2 September 2025
75%+8.1 pts
12 May 2025
67%+17 pts
17 December 2024
50%+16 pts
9 September 2024
34%+24 pts
4 January 2024
9.9%+9.9 pts
23 November 2022
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
National Properties has 1 project under construction in Dubai; 1 has passed its registered completion date.
Own a unit in 399 Hills Park B?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the 399 Hills Park B handover date?
- Construction of 399 Hills Park B is recorded as complete, with a registered completion date of October 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on 399 Hills Park B?
- 399 Hills Park B was 100% built at the site inspection on 31 July 2026. The site has been inspected 9 times since November 2022. The Land Department took 84 site photos at its inspections.
- Is 399 Hills Park B delayed?
- The register lists construction as complete.
- Who is building 399 Hills Park B?
- The registered developer is National Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for 399 Hills Park B?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 161 Jumeirah LaneAlso by National Properties. 70%, Due March 2026, passed.
- Greenside ResidenceNearby in Dubai Hills Estate. 97%.
- Parkside HillsNearby in Dubai Hills Estate. 68%, Due June 2028.
- Park LaneNearby in Dubai Hills Estate. 55%, Due October 2028.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)