Volta Tower construction progress
Volta Tower in Downtown Dubai is 29% built at the Land Department inspection of August 2026. Developer Damac C S L Investment. Completion registered for December 2027.
29%
Built, at the Land Department site inspection of 18 August 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- December 2029
- Construction started
- December 2023
- Registered with the Land Department
- September 2023
- Developer
- Damac C S L Investment
- Community
- Downtown Dubai
- Units
- 417
- Escrow bank
- Emirates NBD
- Name in Arabic
- فولتا تاور
- Land Department project number
- 2782
- Land Department site inspections
- 8
Schedule
Between December 2025 and August 2026 the site added about 1.8 points a month. At that rate it would finish around December 2029, more than three months after the December 2027 date registered with the Land Department.
Site inspections
18 August 2026
29%+8.5 pts
11 April 2026
21%+5.9 pts
11 December 2025
15%+2.0 pts
4 August 2025
13%+5.3 pts
10 April 2025
7.6%+2.3 pts
20 November 2024
5.2%+4.1 pts
5 July 2024
1.1%+1.1 pts
14 September 2023
0%
Context
Downtown Dubai has 13 projects under construction, 33% built on average.
Own a unit in Volta Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Volta Tower be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around December 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Volta Tower is built?
- 29%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 8 times since September 2023.
- Is Volta Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Volta Tower?
- The registered developer is Damac C S L Investment.
- Which bank holds the escrow account for Volta Tower?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiNearby in Downtown Dubai. 76%, Due December 2026.
- City Center ResidencesNearby in Downtown Dubai. 72%, Due September 2026, passed.
- Mercedes-Benz Places | BinghattiNearby in Downtown Dubai. 65%, Due December 2026.
- Baccarat Hotel And Residences, DubaiNearby in Downtown Dubai. 21%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)