Volta Tower construction progress

The registered completion date for Volta Tower in Downtown Dubai is December 2027. At the last site inspection, in August 2026, it was 29% built. The developer is Damac C S L Investment.

29%

Built, at the site inspection of 18 August 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
December 2029
Construction started
December 2023
First registered
September 2023
Developer
Damac C S L Investment
Units
417
Escrow bank
Emirates NBD
Name in Arabic
فولتا تاور
Project number
2782
Site inspections
8

Schedule

Between December 2025 and August 2026 the site added about 1.8 points a month. At that rate it would finish around December 2029, more than three months after its registered date of December 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 August 2026

29%+8.5 pts

  • Volta Tower construction site, inspection photo 1, 18 August 2026
  • Volta Tower construction site, inspection photo 2, 18 August 2026
  • Volta Tower construction site, inspection photo 3, 18 August 2026
  • Volta Tower construction site, inspection photo 4, 18 August 2026

11 April 2026

21%+5.9 pts

  • Volta Tower construction site, inspection photo 1, 11 April 2026
  • Volta Tower construction site, inspection photo 2, 11 April 2026
  • Volta Tower construction site, inspection photo 3, 11 April 2026
  • Volta Tower construction site, inspection photo 4, 11 April 2026

11 December 2025

15%+2.0 pts

  • Volta Tower construction site, inspection photo 1, 11 December 2025
  • Volta Tower construction site, inspection photo 2, 11 December 2025
  • Volta Tower construction site, inspection photo 3, 11 December 2025

4 August 2025

13%+5.3 pts

  • Volta Tower construction site, inspection photo 1, 4 August 2025
  • Volta Tower construction site, inspection photo 2, 4 August 2025
  • Volta Tower construction site, inspection photo 3, 4 August 2025
  • Volta Tower construction site, inspection photo 4, 4 August 2025

10 April 2025

7.6%+2.3 pts

  • Volta Tower construction site, inspection photo 1, 10 April 2025
  • Volta Tower construction site, inspection photo 2, 10 April 2025
  • Volta Tower construction site, inspection photo 3, 10 April 2025
  • Volta Tower construction site, inspection photo 4, 10 April 2025

20 November 2024

5.2%+4.1 pts

  • Volta Tower construction site, inspection photo 1, 20 November 2024
  • Volta Tower construction site, inspection photo 2, 20 November 2024
  • Volta Tower construction site, inspection photo 3, 20 November 2024
  • Volta Tower construction site, inspection photo 4, 20 November 2024

5 July 2024

1.1%+1.1 pts

  • Volta Tower construction site, inspection photo 1, 5 July 2024
  • Volta Tower construction site, inspection photo 2, 5 July 2024
  • Volta Tower construction site, inspection photo 3, 5 July 2024

14 September 2023

0%

  • Volta Tower construction site, inspection photo 1, 14 September 2023
  • Volta Tower construction site, inspection photo 2, 14 September 2023

All 41 site photos, by inspection date

Context

Downtown Dubai has 13 projects under construction, 35% built on average.

Own a unit in Volta Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Volta Tower handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Volta Tower?
Volta Tower was 29% built at the site inspection on 18 August 2026. The site has been inspected 8 times since September 2023. The Land Department took 41 site photos at its inspections.
Is Volta Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Volta Tower?
The registered developer is Damac C S L Investment.
Which bank holds the escrow account for Volta Tower?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.