Exquisite Living Residences construction progress
The register lists Exquisite Living Residences in DownTown Dubai as complete, with a registered completion date of December 2025. Its last site inspection on record was in July 2026. The developer is Zuari Infraworld S J M Properties.
100%
Built, at the site inspection of 13 July 2026
Construction complete
- Registered completion date
- December 2025
- Construction started
- December 2022
- First registered
- February 2023
- Developer
- Zuari Infraworld S J M Properties
- Community
- DownTown Dubai
- Units
- 235
- Escrow bank
- Emirates NBD
- Name in Arabic
- اكسكوزيت ليفينج ريذيدنسز
- Project number
- 2527
- Site inspections
- 14
Schedule
The register lists Exquisite Living Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
13 July 2026
100%+3.7 pts
2 June 2026
96%+6.2 pts
14 January 2026
90%+9.4 pts
22 September 2025
81%+13 pts
6 May 2025
68%+13 pts
17 January 2025
55%+8.3 pts
15 October 2024
47%+15 pts
4 July 2024
32%+6.5 pts
20 March 2024
25%+8.0 pts
20 November 2023
17%+4.6 pts
Context
DownTown Dubai has 13 projects under construction, 35% built on average.
Own a unit in Exquisite Living Residences?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Exquisite Living Residences handover date?
- Construction of Exquisite Living Residences is recorded as complete, with a registered completion date of December 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Exquisite Living Residences?
- Exquisite Living Residences was 100% built at the site inspection on 13 July 2026. The site has been inspected 14 times since December 2022. The Land Department took 89 site photos at its inspections.
- Is Exquisite Living Residences delayed?
- The register lists construction as complete.
- Who is building Exquisite Living Residences?
- The registered developer is Zuari Infraworld S J M Properties.
- Which bank holds the escrow account for Exquisite Living Residences?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiNearby in DownTown Dubai. 76%, Due December 2026.
- City Center ResidencesNearby in DownTown Dubai. 72%, Due September 2026, passed.
- Mercedes-Benz Places | BinghattiNearby in DownTown Dubai. 65%, Due December 2026.
- Baccarat Hotel And Residences, DubaiNearby in DownTown Dubai. 21%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
































.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)