Elite Downtown Residence construction progress

The register lists Elite Downtown Residence in DownTown Dubai as complete, with a registered completion date of February 2022. Its last site inspection on record was in February 2022. The developer is Triplanet Elite Developements.

100%

Built, at the site inspection of 10 February 2022

Construction complete

Registered completion date
February 2022
Construction started
December 2013
First registered
January 2014
Developer
Triplanet Elite Developements
Units
469
Escrow bank
Mashreq Bank
Name in Arabic
ايليت داون تاون رزيدنس
Project number
1403
Site inspections
10

Schedule

The register lists Elite Downtown Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20142016201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 February 2022

100%+28 pts

  • Elite Downtown Residence construction site, inspection photo 1, 10 February 2022
  • Elite Downtown Residence construction site, inspection photo 2, 10 February 2022
  • Elite Downtown Residence construction site, inspection photo 3, 10 February 2022
  • Elite Downtown Residence construction site, inspection photo 4, 10 February 2022

12 September 2021

72%+26 pts

  • Elite Downtown Residence construction site, inspection photo 1, 12 September 2021
  • Elite Downtown Residence construction site, inspection photo 2, 12 September 2021
  • Elite Downtown Residence construction site, inspection photo 3, 12 September 2021
  • Elite Downtown Residence construction site, inspection photo 4, 12 September 2021

17 March 2021

46%+11 pts

  • Elite Downtown Residence construction site, inspection photo 1, 17 March 2021
  • Elite Downtown Residence construction site, inspection photo 2, 17 March 2021
  • Elite Downtown Residence construction site, inspection photo 3, 17 March 2021
  • Elite Downtown Residence construction site, inspection photo 4, 17 March 2021

5 November 2020

35%+2.4 pts

  • Elite Downtown Residence construction site, inspection photo 1, 5 November 2020
  • Elite Downtown Residence construction site, inspection photo 2, 5 November 2020
  • Elite Downtown Residence construction site, inspection photo 3, 5 November 2020
  • Elite Downtown Residence construction site, inspection photo 4, 5 November 2020

10 May 2020

33%+6.0 pts

  • Elite Downtown Residence construction site, inspection photo 1, 10 May 2020
  • Elite Downtown Residence construction site, inspection photo 2, 10 May 2020
  • Elite Downtown Residence construction site, inspection photo 3, 10 May 2020
  • Elite Downtown Residence construction site, inspection photo 4, 10 May 2020

18 February 2019

27%+6.3 pts

  • Elite Downtown Residence construction site, inspection photo 1, 18 February 2019
  • Elite Downtown Residence construction site, inspection photo 2, 18 February 2019
  • Elite Downtown Residence construction site, inspection photo 3, 18 February 2019
  • Elite Downtown Residence construction site, inspection photo 4, 18 February 2019

28 February 2018

20%+7.0 pts

  • Elite Downtown Residence construction site, inspection photo 1, 28 February 2018
  • Elite Downtown Residence construction site, inspection photo 2, 28 February 2018
  • Elite Downtown Residence construction site, inspection photo 3, 28 February 2018
  • Elite Downtown Residence construction site, inspection photo 4, 28 February 2018

18 October 2017

13%+10 pts

  • Elite Downtown Residence construction site, inspection photo 1, 18 October 2017
  • Elite Downtown Residence construction site, inspection photo 2, 18 October 2017
  • Elite Downtown Residence construction site, inspection photo 3, 18 October 2017
  • Elite Downtown Residence construction site, inspection photo 4, 18 October 2017

27 December 2016

3.3%+2.6 pts

  • Elite Downtown Residence construction site, inspection photo 1, 27 December 2016
  • Elite Downtown Residence construction site, inspection photo 2, 27 December 2016
  • Elite Downtown Residence construction site, inspection photo 3, 27 December 2016
  • Elite Downtown Residence construction site, inspection photo 4, 27 December 2016

9 August 2016

0.7%

  • Elite Downtown Residence construction site, inspection photo 1, 9 August 2016
  • Elite Downtown Residence construction site, inspection photo 2, 9 August 2016
  • Elite Downtown Residence construction site, inspection photo 3, 9 August 2016
  • Elite Downtown Residence construction site, inspection photo 4, 9 August 2016

All 84 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Own a unit in Elite Downtown Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Elite Downtown Residence handover date?
Construction of Elite Downtown Residence is recorded as complete, with a registered completion date of February 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Elite Downtown Residence?
Elite Downtown Residence was 100% built at the site inspection on 10 February 2022. The site has been inspected 10 times since August 2016. The Land Department took 84 site photos at its inspections.
Is Elite Downtown Residence delayed?
The register lists construction as complete.
Who is building Elite Downtown Residence?
The registered developer is Triplanet Elite Developements.
Which bank holds the escrow account for Elite Downtown Residence?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.