Baccarat Hotel And Residences, Dubai construction photos

42 photos from 7 site inspections, newest first. The percentage is how much of Baccarat Hotel And Residences, Dubai was built on the day of each visit.

3 September 202621% built

2 June 202618% built

29 January 202613% built

14 October 20259.3% built

4 June 20257.3% built

6 December 20246.5% built

28 July 20230% built

Back to Baccarat Hotel And Residences, Dubai construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.