Suberbia construction progress
The register lists Suberbia in Down Town Jabal Ali as complete, with a registered completion date of March 2013. Its last site inspection on record was in June 2013. The developer is Damac Crown Properties Limited.
100%
Built, at the site inspection of 12 June 2013
Construction complete
- Registered completion date
- March 2013
- Construction started
- April 2010
- First registered
- April 2010
- Developer
- Damac Crown Properties Limited
- Community
- Down Town Jabal Ali
- Units
- 387
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- سبربيى
- Project number
- 422
- Site inspections
- 2
Schedule
The register lists Suberbia as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
12 June 2013
98%+9.0 pts
28 August 2012
89%
Context
Down Town Jabal Ali has 4 projects under construction, 6.5% built on average.
Own a unit in Suberbia?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Suberbia handover date?
- Construction of Suberbia is recorded as complete, with a registered completion date of March 2013. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Suberbia?
- Suberbia was 100% built at the site inspection on 12 June 2013. The site has been inspected 2 times since August 2012. The Land Department took 31 site photos at its inspections.
- Is Suberbia delayed?
- The register lists construction as complete.
- Who is building Suberbia?
- The registered developer is Damac Crown Properties Limited.
- Which bank holds the escrow account for Suberbia?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eleve By DeyaarNearby in Down Town Jabal Ali. 20%.
- Arian By AziziNearby in Down Town Jabal Ali. 2.0%, Due January 2028.
- Azizi AbrahamNearby in Down Town Jabal Ali. 2.0%, Due August 2027.
- Azizi WaresNearby in Down Town Jabal Ali. 2.0%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
