Suberbia construction progress

The register lists Suberbia in Down Town Jabal Ali as complete, with a registered completion date of March 2013. Its last site inspection on record was in June 2013. The developer is Damac Crown Properties Limited.

100%

Built, at the site inspection of 12 June 2013

Construction complete

Registered completion date
March 2013
Construction started
April 2010
First registered
April 2010
Developer
Damac Crown Properties Limited
Units
387
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سبربيى
Project number
422
Site inspections
2

Schedule

The register lists Suberbia as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201120122013
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 June 2013

98%+9.0 pts

  • Suberbia construction site, inspection photo 1, 12 June 2013
  • Suberbia construction site, inspection photo 2, 12 June 2013
  • Suberbia construction site, inspection photo 3, 12 June 2013
  • Suberbia construction site, inspection photo 4, 12 June 2013

28 August 2012

89%

  • Suberbia construction site, inspection photo 1, 28 August 2012
  • Suberbia construction site, inspection photo 2, 28 August 2012
  • Suberbia construction site, inspection photo 3, 28 August 2012
  • Suberbia construction site, inspection photo 4, 28 August 2012

All 31 site photos, by inspection date

Context

Down Town Jabal Ali has 4 projects under construction, 6.5% built on average.

Own a unit in Suberbia?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Suberbia handover date?
Construction of Suberbia is recorded as complete, with a registered completion date of March 2013. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Suberbia?
Suberbia was 100% built at the site inspection on 12 June 2013. The site has been inspected 2 times since August 2012. The Land Department took 31 site photos at its inspections.
Is Suberbia delayed?
The register lists construction as complete.
Who is building Suberbia?
The registered developer is Damac Crown Properties Limited.
Which bank holds the escrow account for Suberbia?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.