Sobha Central Phase Ii construction progress

Sobha Central Phase Ii in Dmcc-ez2 is 6.4% built at the Land Department inspection of September 2026. Developer Sobha. Completion registered for June 2030.

6.4%

Built, at the Land Department site inspection of 29 September 2026

Running behind its date

Completion date (Land Department)
June 2030
Finish at recent pace
May 2038
Construction started
October 2025
Registered with the Land Department
September 2025
Developer
Sobha
Community
Dmcc-ez2
Units
2,143
Escrow bank
Dubai Islamic Bank
Name in Arabic
Ii شوبا سنترال فيز
Land Department project number
4042
Land Department site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around May 2038, more than three months after the June 2030 date registered with the Land Department.

0%25%50%75%100%20262027202820292030
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 September 2026

6.4%+4.1 pts

  • Sobha Central Phase Ii construction site, Land Department inspection photo 1, 29 September 2026
  • Sobha Central Phase Ii construction site, Land Department inspection photo 2, 29 September 2026
  • Sobha Central Phase Ii construction site, Land Department inspection photo 3, 29 September 2026
  • Sobha Central Phase Ii construction site, Land Department inspection photo 4, 29 September 2026

28 March 2026

2.3%+2.3 pts

  • Sobha Central Phase Ii construction site, Land Department inspection photo 1, 28 March 2026
  • Sobha Central Phase Ii construction site, Land Department inspection photo 2, 28 March 2026
  • Sobha Central Phase Ii construction site, Land Department inspection photo 3, 28 March 2026
  • Sobha Central Phase Ii construction site, Land Department inspection photo 4, 28 March 2026

21 August 2025

0%

  • Sobha Central Phase Ii construction site, Land Department inspection photo 1, 21 August 2025
  • Sobha Central Phase Ii construction site, Land Department inspection photo 2, 21 August 2025

All 18 site photos, by inspection date

Context

Dmcc-ez2 has 2 projects under construction, 6.8% built on average. Sobha Central Phase Ii is behind that average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha Central Phase Ii?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Sobha Central Phase Ii be completed?
The completion date registered with the Dubai Land Department is June 2030. At the pace of its recent inspections the site would reach 100% around May 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sobha Central Phase Ii is built?
6.4%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 3 times since August 2025.
Is Sobha Central Phase Ii delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2030.
Who is building Sobha Central Phase Ii?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha Central Phase Ii?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.