Sobha Central Phase Ii construction progress
Sobha Central Phase Ii in Dmcc-ez2 is 6.4% built at the Land Department inspection of September 2026. Developer Sobha. Completion registered for June 2030.
6.4%
Built, at the Land Department site inspection of 29 September 2026
Running behind its date
- Completion date (Land Department)
- June 2030
- Finish at recent pace
- May 2038
- Construction started
- October 2025
- Registered with the Land Department
- September 2025
- Developer
- Sobha
- Community
- Dmcc-ez2
- Units
- 2,143
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- Ii شوبا سنترال فيز
- Land Department project number
- 4042
- Land Department site inspections
- 3
Schedule
Between March 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around May 2038, more than three months after the June 2030 date registered with the Land Department.
Site inspections
29 September 2026
6.4%+4.1 pts
28 March 2026
2.3%+2.3 pts
21 August 2025
0%
Context
Dmcc-ez2 has 2 projects under construction, 6.8% built on average. Sobha Central Phase Ii is behind that average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Central Phase Ii?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Sobha Central Phase Ii be completed?
- The completion date registered with the Dubai Land Department is June 2030. At the pace of its recent inspections the site would reach 100% around May 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sobha Central Phase Ii is built?
- 6.4%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 3 times since August 2025.
- Is Sobha Central Phase Ii delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2030.
- Who is building Sobha Central Phase Ii?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Central Phase Ii?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 37%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vistas HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.