Skip to content

Sobha Central Phase I construction progress

The registered completion date for Sobha Central Phase I in Dmcc-ez2 is June 2030. At the last site inspection, in September 2026, it was 7.1% built. The developer is Sobha.

7.1%

Built, at the site inspection of 29 September 2026

Running behind its date

Registered completion date
June 2030
Finish at recent pace
October 2037
Construction started
August 2025
First registered
July 2025
Developer
Sobha
Community
Dmcc-ez2
Units
2,383
Escrow bank
Dubai Islamic Bank
Name in Arabic
I شوبا سنترال فيز
Project number
3713
Site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around October 2037, more than three months after its registered date of June 2030.

0%25%50%75%100%20262027202820292030
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 September 2026

7.1%+4.3 pts

  • Sobha Central Phase I construction site, inspection photo 1, 29 September 2026
  • Sobha Central Phase I construction site, inspection photo 2, 29 September 2026
  • Sobha Central Phase I construction site, inspection photo 3, 29 September 2026
  • Sobha Central Phase I construction site, inspection photo 4, 29 September 2026

26 March 2026

2.8%+2.8 pts

  • Sobha Central Phase I construction site, inspection photo 1, 26 March 2026
  • Sobha Central Phase I construction site, inspection photo 2, 26 March 2026
  • Sobha Central Phase I construction site, inspection photo 3, 26 March 2026
  • Sobha Central Phase I construction site, inspection photo 4, 26 March 2026

15 July 2025

0%

  • Sobha Central Phase I construction site, inspection photo 1, 15 July 2025
  • Sobha Central Phase I construction site, inspection photo 2, 15 July 2025

All 15 site photos, by inspection date

Context

Dmcc-ez2 has 2 projects under construction, 6.8% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha Central Phase I?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sobha Central Phase I handover date?
The registered completion date is June 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sobha Central Phase I?
Sobha Central Phase I was 7.1% built at the site inspection on 29 September 2026. The site has been inspected 3 times since July 2025. The Land Department took 15 site photos at its inspections.
Is Sobha Central Phase I delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2030.
Who is building Sobha Central Phase I?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha Central Phase I?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.