Damac Lagoons - Portofino construction progress

Damac Lagoons - Portofino in Damac Lagoons is 97% built at the Land Department inspection of July 2026. Developer Island Oasis Properties. Completion registered for June 2025.

97%

Built, at the Land Department site inspection of 16 July 2026

16 months past its registered completion date

Completion date (Land Department)
June 2025
Finish at recent pace
September 2026
Construction started
April 2022
Registered with the Land Department
January 2022
Community
Damac Lagoons
Units
867
Escrow bank
Emirates NBD
Name in Arabic
داماك لاجونر - بورتوفينو
Land Department project number
2356
Land Department site inspections
12

Schedule

Damac Lagoons - Portofino was registered to complete in June 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 1.3 points a month. Kept at that rate, the site would reach 100% around September 2026.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 July 2026

97%+0.2 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 16 July 2026
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 16 July 2026
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 16 July 2026
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 16 July 2026

17 March 2026

97%+6.4 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 17 March 2026
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 17 March 2026
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 17 March 2026
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 17 March 2026

18 November 2025

91%+9.0 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 18 November 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 18 November 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 18 November 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 18 November 2025

24 July 2025

82%+9.5 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 24 July 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 24 July 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 24 July 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 24 July 2025

19 March 2025

72%+1.6 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 19 March 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 19 March 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 19 March 2025
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 19 March 2025

19 November 2024

71%+10 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 19 November 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 19 November 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 19 November 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 19 November 2024

13 September 2024

60%+25 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 13 September 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 13 September 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 13 September 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 13 September 2024

15 March 2024

36%+26 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 15 March 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 15 March 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 15 March 2024
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 15 March 2024

9 October 2023

9.2%+6.9 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 9 October 2023
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 9 October 2023
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 9 October 2023
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 9 October 2023

12 June 2023

2.3%+2.0 pts

  • Damac Lagoons - Portofino construction site, Land Department inspection photo 1, 12 June 2023
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 2, 12 June 2023
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 3, 12 June 2023
  • Damac Lagoons - Portofino construction site, Land Department inspection photo 4, 12 June 2023

All 82 site photos, by inspection date

Context

Damac Lagoons has 6 projects under construction, 82% built on average.

Island Oasis Properties has 27 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Damac Lagoons - Portofino?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Damac Lagoons - Portofino be completed?
The completion date registered with the Dubai Land Department is June 2025. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Lagoons - Portofino is built?
97%, measured at the Land Department site inspection on 16 July 2026. The Land Department engineers have inspected the site 12 times since September 2022.
Is Damac Lagoons - Portofino delayed?
Yes. Its registered completion date of June 2025 has passed and the Land Department still lists it as under construction.
Who is building Damac Lagoons - Portofino?
The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Portofino?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.