Damac Hills (2) - Juniper construction progress
The register lists Damac Hills (2) - Juniper in Damac Hills 2 as complete, with a registered completion date of September 2019. Its last site inspection on record was in September 2019. The developer is Front Line Investment Management.
100%
Built, at the site inspection of 17 September 2019
Construction complete
- Registered completion date
- September 2019
- Construction started
- January 2015
- First registered
- August 2014
- Developer
- Front Line Investment Management
- Community
- Damac Hills 2
- Units
- 313
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- داماك هيلز (2) - جونيبر
- Project number
- 1550
- Site inspections
- 13
Schedule
The register lists Damac Hills (2) - Juniper as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
17 September 2019
100%+2.9 pts
19 June 2019
97%+6.1 pts
20 January 2019
91%+5.5 pts
9 October 2018
86%+4.0 pts
11 June 2018
82%+17 pts
14 February 2018
65%+4.6 pts
8 October 2017
60%+5.5 pts
13 August 2017
55%+3.2 pts
3 July 2017
51%+16 pts
17 January 2017
35%+11 pts
Context
Damac Hills 2 has 12 projects under construction, 49% built on average.
Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Damac Hills (2) - Juniper?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Damac Hills (2) - Juniper handover date?
- Construction of Damac Hills (2) - Juniper is recorded as complete, with a registered completion date of September 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Damac Hills (2) - Juniper?
- Damac Hills (2) - Juniper was 100% built at the site inspection on 17 September 2019. The site has been inspected 13 times since February 2015. The Land Department took 87 site photos at its inspections.
- Is Damac Hills (2) - Juniper delayed?
- The register lists construction as complete.
- Who is building Damac Hills (2) - Juniper?
- The registered developer is Front Line Investment Management. It has 12 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Hills (2) - Juniper?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Hills (2) - FarmhousesAlso by Front Line Investment Management. 83%, Due August 2025, passed.
- Damac Hills (2) - VioletAlso by Front Line Investment Management. 95%.
- Damac Hills (2) - NaturaAlso by Front Line Investment Management. 86%.
- Damac Hills (2) - Park Greens 3Also by Front Line Investment Management. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.