Damac Hills (2) - Park Greens 3 construction progress

No completion date is registered for Damac Hills (2) - Park Greens 3 in Damac Hills 2 yet. At the last site inspection, in October 2026, it was 51% built. The developer is Front Line Investment Management.

51%

Built, at the site inspection of 30 October 2026

Finish at recent pace
February 2028
Construction started
February 2024
First registered
December 2023
Community
Damac Hills 2
Units
385
Escrow bank
Emirates NBD
Name in Arabic
داماك هيلز (2) - بارك جرينز 3
Project number
2857
Site inspections
5

Schedule

Since May 2026 Damac Hills (2) - Park Greens 3 has added about 3.1 points a month. At that rate the site reaches 100% around February 2028. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

30 October 2026

51%+17 pts

  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 1, 30 October 2026
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 2, 30 October 2026
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 3, 30 October 2026
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 4, 30 October 2026

12 May 2026

33%+28 pts

  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 1, 12 May 2026
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 2, 12 May 2026
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 3, 12 May 2026
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 4, 12 May 2026

9 July 2025

5.5%+4.9 pts

  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 1, 9 July 2025
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 2, 9 July 2025
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 3, 9 July 2025
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 4, 9 July 2025

5 July 2024

0.5%+0.5 pts

  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 1, 5 July 2024
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 2, 5 July 2024

20 November 2023

0%

  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 1, 20 November 2023
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 2, 20 November 2023
  • Damac Hills (2) - Park Greens 3 construction site, inspection photo 3, 20 November 2023

All 33 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 49% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Park Greens 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Hills (2) - Park Greens 3 handover date?
No completion date is on record for Damac Hills (2) - Park Greens 3 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Damac Hills (2) - Park Greens 3?
Damac Hills (2) - Park Greens 3 was 51% built at the site inspection on 30 October 2026. The site has been inspected 5 times since November 2023. The Land Department took 33 site photos at its inspections.
Who is building Damac Hills (2) - Park Greens 3?
The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Park Greens 3?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.