Damac Hills (2) - Farmhouses construction progress

Damac Hills (2) - Farmhouses in Damac Hills 2 was registered to complete in August 2025 and is still under construction. At the last site inspection, in May 2026, it was 83% built. The developer is Front Line Investment Management.

83%

Built, at the site inspection of 14 May 2026

15 months past its registered completion date

Registered completion date
August 2025
Finish at recent pace
October 2026
Construction started
September 2023
First registered
July 2023
Community
Damac Hills 2
Units
13
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
داماك هيلز (2) - فارم هاوسيز
Project number
2543
Site inspections
6

Schedule

Damac Hills (2) - Farmhouses was registered to complete in August 2025, 15 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around October 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 May 2026

83%+24 pts

  • Damac Hills (2) - Farmhouses construction site, inspection photo 1, 14 May 2026
  • Damac Hills (2) - Farmhouses construction site, inspection photo 2, 14 May 2026
  • Damac Hills (2) - Farmhouses construction site, inspection photo 3, 14 May 2026
  • Damac Hills (2) - Farmhouses construction site, inspection photo 4, 14 May 2026

25 November 2025

59%+14 pts

  • Damac Hills (2) - Farmhouses construction site, inspection photo 1, 25 November 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 2, 25 November 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 3, 25 November 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 4, 25 November 2025

25 June 2025

45%+15 pts

  • Damac Hills (2) - Farmhouses construction site, inspection photo 1, 25 June 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 2, 25 June 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 3, 25 June 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 4, 25 June 2025

25 February 2025

30%+29 pts

  • Damac Hills (2) - Farmhouses construction site, inspection photo 1, 25 February 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 2, 25 February 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 3, 25 February 2025
  • Damac Hills (2) - Farmhouses construction site, inspection photo 4, 25 February 2025

14 March 2024

1.3%+1.3 pts

  • Damac Hills (2) - Farmhouses construction site, inspection photo 1, 14 March 2024
  • Damac Hills (2) - Farmhouses construction site, inspection photo 2, 14 March 2024
  • Damac Hills (2) - Farmhouses construction site, inspection photo 3, 14 March 2024

9 January 2023

0%

  • Damac Hills (2) - Farmhouses construction site, inspection photo 1, 9 January 2023
  • Damac Hills (2) - Farmhouses construction site, inspection photo 2, 9 January 2023

All 32 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 49% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Farmhouses?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Hills (2) - Farmhouses handover date?
The registered completion date was August 2025, and the register still lists Damac Hills (2) - Farmhouses as under construction. At the pace of its recent inspections the site would reach 100% around October 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Hills (2) - Farmhouses?
Damac Hills (2) - Farmhouses was 83% built at the site inspection on 14 May 2026. The site has been inspected 6 times since January 2023. The Land Department took 32 site photos at its inspections.
Is Damac Hills (2) - Farmhouses delayed?
Yes. Its registered completion date of August 2025 has passed and the project is still listed as under construction.
Who is building Damac Hills (2) - Farmhouses?
The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Farmhouses?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.