Damac Hills (2) - Juniper construction photos

87 photos from 13 site inspections, newest first. The percentage is how much of Damac Hills (2) - Juniper was built on the day of each visit.

17 September 2019100% built

19 June 201997% built

20 January 201991% built

9 October 201886% built

11 June 201882% built

14 February 201865% built

8 October 201760% built

13 August 201755% built

3 July 201751% built

17 January 201735% built

9 August 201624% built

11 November 20154.2% built

25 February 20152.3% built

Back to Damac Hills (2) - Juniper construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.