Damac Hills (2) - Evergreens construction progress
No completion date is registered for Damac Hills (2) - Evergreens in Damac Hills 2 yet. At the last site inspection, in October 2026, it was 48% built. The developer is Front Line Investment Management.
48%
Built, at the site inspection of 30 October 2026
- Finish at recent pace
- March 2028
- Construction started
- July 2024
- First registered
- May 2024
- Developer
- Front Line Investment Management
- Community
- Damac Hills 2
- Units
- 131
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك هيلز (2) - ايفرجرينز
- Project number
- 3092
- Site inspections
- 5
Schedule
Since December 2025 Damac Hills (2) - Evergreens has added about 3.1 points a month. At that rate the site reaches 100% around March 2028. No completion date is on record to compare it with.
Site inspections
30 October 2026
48%+22 pts
5 May 2026
26%+9.2 pts
26 December 2025
17%+17 pts
15 April 2025
0.1%+0.1 pts
14 May 2024
0%
Context
Damac Hills 2 has 12 projects under construction, 49% built on average.
Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Damac Hills (2) - Evergreens?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Damac Hills (2) - Evergreens handover date?
- No completion date is on record for Damac Hills (2) - Evergreens yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Damac Hills (2) - Evergreens?
- Damac Hills (2) - Evergreens was 48% built at the site inspection on 30 October 2026. The site has been inspected 5 times since May 2024. The Land Department took 26 site photos at its inspections.
- Who is building Damac Hills (2) - Evergreens?
- The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Hills (2) - Evergreens?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Hills (2) - FarmhousesAlso by Front Line Investment Management. 83%, Due August 2025, passed.
- Damac Hills (2) - VioletAlso by Front Line Investment Management. 95%.
- Damac Hills (2) - NaturaAlso by Front Line Investment Management. 86%.
- Damac Hills (2) - Park Greens 3Also by Front Line Investment Management. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.