Damac Hills (2) - Evergreens construction photos

17 photos taken by Dubai Land Department engineers at 4 site inspections, newest first. The percentage is how much of Damac Hills (2) - Evergreens was built on the day of each visit.

5 May 202626% built

26 December 202517% built

15 April 20250.1% built

14 May 20240% built

Back to Damac Hills (2) - Evergreens construction progress