Damac Hills (2) - Elo construction progress

No completion date is registered for Damac Hills (2) - Elo in Damac Hills 2 yet. At the last site inspection, in October 2026, it was 32% built. The developer is Front Line Investment Management.

32%

Built, at the site inspection of 30 October 2026

Finish at recent pace
January 2030
Construction started
July 2024
First registered
June 2024
Community
Damac Hills 2
Units
557
Escrow bank
Emirates NBD
Name in Arabic
داماك هيلز (2) - ايلو
Project number
2995
Site inspections
5

Schedule

Since December 2025 Damac Hills (2) - Elo has added about 1.8 points a month. At that rate the site reaches 100% around January 2030. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

30 October 2026

32%+10 pts

  • Damac Hills (2) - Elo construction site, inspection photo 1, 30 October 2026
  • Damac Hills (2) - Elo construction site, inspection photo 2, 30 October 2026
  • Damac Hills (2) - Elo construction site, inspection photo 3, 30 October 2026
  • Damac Hills (2) - Elo construction site, inspection photo 4, 30 October 2026

15 April 2026

22%+8.1 pts

  • Damac Hills (2) - Elo construction site, inspection photo 1, 15 April 2026
  • Damac Hills (2) - Elo construction site, inspection photo 2, 15 April 2026
  • Damac Hills (2) - Elo construction site, inspection photo 3, 15 April 2026
  • Damac Hills (2) - Elo construction site, inspection photo 4, 15 April 2026

26 December 2025

13%+12 pts

  • Damac Hills (2) - Elo construction site, inspection photo 1, 26 December 2025
  • Damac Hills (2) - Elo construction site, inspection photo 2, 26 December 2025
  • Damac Hills (2) - Elo construction site, inspection photo 3, 26 December 2025
  • Damac Hills (2) - Elo construction site, inspection photo 4, 26 December 2025

24 April 2025

1.2%+1.2 pts

  • Damac Hills (2) - Elo construction site, inspection photo 1, 24 April 2025
  • Damac Hills (2) - Elo construction site, inspection photo 2, 24 April 2025
  • Damac Hills (2) - Elo construction site, inspection photo 3, 24 April 2025
  • Damac Hills (2) - Elo construction site, inspection photo 4, 24 April 2025

28 May 2024

0%

  • Damac Hills (2) - Elo construction site, inspection photo 1, 28 May 2024
  • Damac Hills (2) - Elo construction site, inspection photo 2, 28 May 2024
  • Damac Hills (2) - Elo construction site, inspection photo 3, 28 May 2024

All 27 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 49% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Elo?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Hills (2) - Elo handover date?
No completion date is on record for Damac Hills (2) - Elo yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Damac Hills (2) - Elo?
Damac Hills (2) - Elo was 32% built at the site inspection on 30 October 2026. The site has been inspected 5 times since May 2024. The Land Department took 27 site photos at its inspections.
Who is building Damac Hills (2) - Elo?
The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Elo?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.