Damac Hills (2) - Elo construction photos
27 photos from 5 site inspections, newest first. The percentage is how much of Damac Hills (2) - Elo was built on the day of each visit.
30 October 202632% built
15 April 202622% built
26 December 202513% built
24 April 20251.2% built
28 May 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.