Damac Hills (2) - Amargo 2 construction progress

The register lists Damac Hills (2) - Amargo 2 in Damac Hills 2 as complete, with a registered completion date of January 2024. Its last site inspection on record was in June 2024. The developer is Front Line Investment Management.

100%

Built, at the site inspection of 6 June 2024

Construction complete

Registered completion date
January 2024
Construction started
May 2022
First registered
February 2022
Community
Damac Hills 2
Units
105
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
داماك هيلز 2 - أمارجو 2
Project number
2357
Site inspections
5

Schedule

The register lists Damac Hills (2) - Amargo 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 June 2024

100%+42 pts

  • Damac Hills (2) - Amargo 2 construction site, inspection photo 1, 6 June 2024
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 2, 6 June 2024
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 3, 6 June 2024
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 4, 6 June 2024

8 November 2023

58%+18 pts

  • Damac Hills (2) - Amargo 2 construction site, inspection photo 1, 8 November 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 2, 8 November 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 3, 8 November 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 4, 8 November 2023

19 July 2023

40%+13 pts

  • Damac Hills (2) - Amargo 2 construction site, inspection photo 1, 19 July 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 2, 19 July 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 3, 19 July 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 4, 19 July 2023

27 February 2023

28%+23 pts

  • Damac Hills (2) - Amargo 2 construction site, inspection photo 1, 27 February 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 2, 27 February 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 3, 27 February 2023
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 4, 27 February 2023

15 September 2022

5.0%

  • Damac Hills (2) - Amargo 2 construction site, inspection photo 1, 15 September 2022
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 2, 15 September 2022
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 3, 15 September 2022
  • Damac Hills (2) - Amargo 2 construction site, inspection photo 4, 15 September 2022

All 43 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 49% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Amargo 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Damac Hills (2) - Amargo 2 handover date?
Construction of Damac Hills (2) - Amargo 2 is recorded as complete, with a registered completion date of January 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Damac Hills (2) - Amargo 2?
Damac Hills (2) - Amargo 2 was 100% built at the site inspection on 6 June 2024. The site has been inspected 5 times since September 2022. The Land Department took 43 site photos at its inspections.
Is Damac Hills (2) - Amargo 2 delayed?
The register lists construction as complete.
Who is building Damac Hills (2) - Amargo 2?
The registered developer is Front Line Investment Management. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Amargo 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.