43 photos from 5 site inspections, newest first. The percentage is how much of Damac Hills (2) - Amargo 2 was built on the day of each visit.

6 June 2024100% built

8 November 202358% built

19 July 202340% built

27 February 202328% built

15 September 20225.0% built

Back to Damac Hills (2) - Amargo 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.