City Walk Crestlane 2 construction progress

City Walk Crestlane 2 in City Walk is 5.2% built at the Land Department inspection of June 2026. Developer Citywalk Residential 1. Completion registered for December 2028.

6.8%

Built, at the Land Department site inspection of 12 June 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
December 2040
Construction started
April 2025
Registered with the Land Department
February 2025
Community
City Walk
Units
203
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سيتي ووك كريستلين 2
Land Department project number
3530
Land Department site inspections
5

Schedule

Between August 2025 and June 2026 the site added about 0.5 points a month. At that rate it would finish around December 2040, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

12 June 2026

5.2%+4.1 pts

  • City Walk Crestlane 2 construction site, Land Department inspection photo 1, 12 June 2026
  • City Walk Crestlane 2 construction site, Land Department inspection photo 2, 12 June 2026
  • City Walk Crestlane 2 construction site, Land Department inspection photo 3, 12 June 2026
  • City Walk Crestlane 2 construction site, Land Department inspection photo 4, 12 June 2026

10 March 2026

1.1%+1.1 pts

  • City Walk Crestlane 2 construction site, Land Department inspection photo 1, 10 March 2026
  • City Walk Crestlane 2 construction site, Land Department inspection photo 2, 10 March 2026

19 November 2025

0%+0.0 pts

  • City Walk Crestlane 2 construction site, Land Department inspection photo 1, 19 November 2025
  • City Walk Crestlane 2 construction site, Land Department inspection photo 2, 19 November 2025
  • City Walk Crestlane 2 construction site, Land Department inspection photo 3, 19 November 2025

25 August 2025

0%

  • City Walk Crestlane 2 construction site, Land Department inspection photo 1, 25 August 2025
  • City Walk Crestlane 2 construction site, Land Department inspection photo 2, 25 August 2025

31 January 2025

0%

  • City Walk Crestlane 2 construction site, Land Department inspection photo 1, 31 January 2025
  • City Walk Crestlane 2 construction site, Land Department inspection photo 2, 31 January 2025

All 14 site photos, by inspection date

Context

City Walk has 7 projects under construction, 21% built on average.

Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in City Walk Crestlane 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will City Walk Crestlane 2 be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around December 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of City Walk Crestlane 2 is built?
6.8%, measured at the Land Department site inspection on 12 June 2026. The Land Department engineers have inspected the site 5 times since January 2025.
Is City Walk Crestlane 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building City Walk Crestlane 2?
The registered developer is Citywalk Residential 1. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for City Walk Crestlane 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.