Fern construction progress

The register lists Fern in City Walk as complete, with a registered completion date of March 2026. Its last site inspection on record was in September 2026. The developer is Citywalk Residential 1.

100%

Built, at the site inspection of 30 September 2026

Construction complete

Registered completion date
March 2026
Construction started
December 2022
First registered
October 2022
Community
City Walk
Units
214
Escrow bank
Commercial Bank of Dubai
Name in Arabic
فيرن
Project number
2481
Site inspections
12

Schedule

The register lists Fern as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2026

100%+2.8 pts

  • Fern construction site, inspection photo 1, 30 September 2026
  • Fern construction site, inspection photo 2, 30 September 2026
  • Fern construction site, inspection photo 3, 30 September 2026
  • Fern construction site, inspection photo 4, 30 September 2026

7 September 2026

97%+6.0 pts

  • Fern construction site, inspection photo 1, 7 September 2026
  • Fern construction site, inspection photo 2, 7 September 2026
  • Fern construction site, inspection photo 3, 7 September 2026
  • Fern construction site, inspection photo 4, 7 September 2026

13 May 2026

91%+3.5 pts

  • Fern construction site, inspection photo 1, 13 May 2026
  • Fern construction site, inspection photo 2, 13 May 2026
  • Fern construction site, inspection photo 3, 13 May 2026
  • Fern construction site, inspection photo 4, 13 May 2026

30 January 2026

88%+5.2 pts

  • Fern construction site, inspection photo 1, 30 January 2026
  • Fern construction site, inspection photo 2, 30 January 2026
  • Fern construction site, inspection photo 3, 30 January 2026
  • Fern construction site, inspection photo 4, 30 January 2026

31 October 2025

83%+20 pts

  • Fern construction site, inspection photo 1, 31 October 2025
  • Fern construction site, inspection photo 2, 31 October 2025
  • Fern construction site, inspection photo 3, 31 October 2025
  • Fern construction site, inspection photo 4, 31 October 2025

4 August 2025

62%+12 pts

  • Fern construction site, inspection photo 1, 4 August 2025
  • Fern construction site, inspection photo 2, 4 August 2025
  • Fern construction site, inspection photo 3, 4 August 2025
  • Fern construction site, inspection photo 4, 4 August 2025

13 May 2025

50%+20 pts

  • Fern construction site, inspection photo 1, 13 May 2025
  • Fern construction site, inspection photo 2, 13 May 2025
  • Fern construction site, inspection photo 3, 13 May 2025
  • Fern construction site, inspection photo 4, 13 May 2025

8 February 2025

30%+6.6 pts

  • Fern construction site, inspection photo 1, 8 February 2025
  • Fern construction site, inspection photo 2, 8 February 2025
  • Fern construction site, inspection photo 3, 8 February 2025
  • Fern construction site, inspection photo 4, 8 February 2025

23 September 2024

24%+18 pts

  • Fern construction site, inspection photo 1, 23 September 2024
  • Fern construction site, inspection photo 2, 23 September 2024
  • Fern construction site, inspection photo 3, 23 September 2024
  • Fern construction site, inspection photo 4, 23 September 2024

21 November 2023

5.9%+4.2 pts

  • Fern construction site, inspection photo 1, 21 November 2023
  • Fern construction site, inspection photo 2, 21 November 2023
  • Fern construction site, inspection photo 3, 21 November 2023

All 100 site photos, by inspection date

Context

City Walk has 7 projects under construction, 24% built on average.

Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Fern?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Fern handover date?
Construction of Fern is recorded as complete, with a registered completion date of March 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Fern?
Fern was 100% built at the site inspection on 30 September 2026. The site has been inspected 12 times since October 2022. The Land Department took 100 site photos at its inspections.
Is Fern delayed?
The register lists construction as complete.
Who is building Fern?
The registered developer is Citywalk Residential 1. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Fern?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.