Erin construction progress

The register lists Erin in City Walk as complete, with a registered completion date of August 2026. Its last site inspection on record was in June 2026. The developer is Citywalk Residential 1.

100%

Built, at the site inspection of 10 June 2026

Construction complete

Registered completion date
August 2026
Construction started
April 2023
First registered
January 2023
Community
City Walk
Units
200
Escrow bank
Commercial Bank of Dubai
Name in Arabic
إرين
Project number
2556
Site inspections
10

Schedule

The register lists Erin as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 June 2026

100%+8.7 pts

  • Erin construction site, inspection photo 1, 10 June 2026
  • Erin construction site, inspection photo 2, 10 June 2026
  • Erin construction site, inspection photo 3, 10 June 2026
  • Erin construction site, inspection photo 4, 10 June 2026

12 May 2026

91%+4.2 pts

  • Erin construction site, inspection photo 1, 12 May 2026
  • Erin construction site, inspection photo 2, 12 May 2026
  • Erin construction site, inspection photo 3, 12 May 2026
  • Erin construction site, inspection photo 4, 12 May 2026

9 February 2026

87%+10 pts

  • Erin construction site, inspection photo 1, 9 February 2026
  • Erin construction site, inspection photo 2, 9 February 2026
  • Erin construction site, inspection photo 3, 9 February 2026
  • Erin construction site, inspection photo 4, 9 February 2026

3 November 2025

77%+16 pts

  • Erin construction site, inspection photo 1, 3 November 2025
  • Erin construction site, inspection photo 2, 3 November 2025
  • Erin construction site, inspection photo 3, 3 November 2025
  • Erin construction site, inspection photo 4, 3 November 2025

6 August 2025

61%+14 pts

  • Erin construction site, inspection photo 1, 6 August 2025
  • Erin construction site, inspection photo 2, 6 August 2025
  • Erin construction site, inspection photo 3, 6 August 2025
  • Erin construction site, inspection photo 4, 6 August 2025

13 May 2025

47%+16 pts

  • Erin construction site, inspection photo 1, 13 May 2025
  • Erin construction site, inspection photo 2, 13 May 2025
  • Erin construction site, inspection photo 3, 13 May 2025
  • Erin construction site, inspection photo 4, 13 May 2025

4 February 2025

31%+12 pts

  • Erin construction site, inspection photo 1, 4 February 2025
  • Erin construction site, inspection photo 2, 4 February 2025
  • Erin construction site, inspection photo 3, 4 February 2025
  • Erin construction site, inspection photo 4, 4 February 2025

24 September 2024

20%+17 pts

  • Erin construction site, inspection photo 1, 24 September 2024
  • Erin construction site, inspection photo 2, 24 September 2024
  • Erin construction site, inspection photo 3, 24 September 2024
  • Erin construction site, inspection photo 4, 24 September 2024

21 November 2023

2.6%+2.6 pts

  • Erin construction site, inspection photo 1, 21 November 2023
  • Erin construction site, inspection photo 2, 21 November 2023
  • Erin construction site, inspection photo 3, 21 November 2023

12 January 2023

0%

  • Erin construction site, inspection photo 1, 12 January 2023
  • Erin construction site, inspection photo 2, 12 January 2023
  • Erin construction site, inspection photo 3, 12 January 2023
  • Erin construction site, inspection photo 4, 12 January 2023

All 89 site photos, by inspection date

Context

City Walk has 7 projects under construction, 24% built on average.

Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Erin?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Erin handover date?
Construction of Erin is recorded as complete, with a registered completion date of August 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Erin?
Erin was 100% built at the site inspection on 10 June 2026. The site has been inspected 10 times since January 2023. The Land Department took 89 site photos at its inspections.
Is Erin delayed?
The register lists construction as complete.
Who is building Erin?
The registered developer is Citywalk Residential 1. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Erin?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.