Celadon construction progress

The register lists Celadon in City Walk as complete, with a registered completion date of November 2024. Its last site inspection on record was in September 2025. The developer is Citywalk Residential 1.

100%

Built, at the site inspection of 30 September 2025

Construction complete

Registered completion date
November 2024
Construction started
February 2022
First registered
November 2021
Community
City Walk
Units
161
Escrow bank
Commercial Bank of Dubai
Name in Arabic
سيلادون
Project number
2325
Site inspections
10

Schedule

The register lists Celadon as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2025

100%+1.0 pts

  • Celadon construction site, inspection photo 1, 30 September 2025
  • Celadon construction site, inspection photo 2, 30 September 2025
  • Celadon construction site, inspection photo 3, 30 September 2025
  • Celadon construction site, inspection photo 4, 30 September 2025

26 September 2025

99%+4.7 pts

  • Celadon construction site, inspection photo 1, 26 September 2025
  • Celadon construction site, inspection photo 2, 26 September 2025
  • Celadon construction site, inspection photo 3, 26 September 2025
  • Celadon construction site, inspection photo 4, 26 September 2025

26 August 2025

94%+13 pts

  • Celadon construction site, inspection photo 1, 26 August 2025
  • Celadon construction site, inspection photo 2, 26 August 2025
  • Celadon construction site, inspection photo 3, 26 August 2025
  • Celadon construction site, inspection photo 4, 26 August 2025

13 May 2025

81%+10 pts

  • Celadon construction site, inspection photo 1, 13 May 2025
  • Celadon construction site, inspection photo 2, 13 May 2025
  • Celadon construction site, inspection photo 3, 13 May 2025
  • Celadon construction site, inspection photo 4, 13 May 2025

6 February 2025

71%+51 pts

  • Celadon construction site, inspection photo 1, 6 February 2025
  • Celadon construction site, inspection photo 2, 6 February 2025
  • Celadon construction site, inspection photo 3, 6 February 2025
  • Celadon construction site, inspection photo 4, 6 February 2025

21 March 2024

20%+14 pts

  • Celadon construction site, inspection photo 1, 21 March 2024
  • Celadon construction site, inspection photo 2, 21 March 2024
  • Celadon construction site, inspection photo 3, 21 March 2024
  • Celadon construction site, inspection photo 4, 21 March 2024

15 August 2023

5.9%+1.3 pts

  • Celadon construction site, inspection photo 1, 15 August 2023
  • Celadon construction site, inspection photo 2, 15 August 2023
  • Celadon construction site, inspection photo 3, 15 August 2023

3 May 2023

4.6%+3.6 pts

  • Celadon construction site, inspection photo 1, 3 May 2023
  • Celadon construction site, inspection photo 2, 3 May 2023
  • Celadon construction site, inspection photo 3, 3 May 2023
  • Celadon construction site, inspection photo 4, 3 May 2023

30 January 2023

1.0%+1.0 pts

  • Celadon construction site, inspection photo 1, 30 January 2023
  • Celadon construction site, inspection photo 2, 30 January 2023
  • Celadon construction site, inspection photo 3, 30 January 2023
  • Celadon construction site, inspection photo 4, 30 January 2023

13 October 2022

0%

  • Celadon construction site, inspection photo 1, 13 October 2022
  • Celadon construction site, inspection photo 2, 13 October 2022
  • Celadon construction site, inspection photo 3, 13 October 2022

All 79 site photos, by inspection date

Context

City Walk has 7 projects under construction, 24% built on average.

Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Celadon?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Celadon handover date?
Construction of Celadon is recorded as complete, with a registered completion date of November 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Celadon?
Celadon was 100% built at the site inspection on 30 September 2025. The site has been inspected 10 times since October 2022. The Land Department took 79 site photos at its inspections.
Is Celadon delayed?
The register lists construction as complete.
Who is building Celadon?
The registered developer is Citywalk Residential 1. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Celadon?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.