Damac Sun City construction photos

41 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Damac Sun City was built on the day of each visit.

24 September 202637% built

20 May 202619% built

27 January 20267.1% built

20 August 20253.9% built

15 April 20251.9% built

29 August 20240% built

Back to Damac Sun City construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.