Skip to content

Damac Islands - Seychelles 1 construction progress

The registered completion date for Damac Islands - Seychelles 1 in Al Yelayiss 1 is June 2029. At the last site inspection, in May 2026, it was 2.5% built. The developer is Damac Elite Investment Co.

2.5%

Built, at the site inspection of 1 May 2026

Running behind its date

Registered completion date
June 2029
Finish at recent pace
July 2049
Construction started
October 2025
First registered
May 2025
Community
Al Yelayiss 1
Units
204
Escrow bank
Emirates NBD
Name in Arabic
1 داماك ايلاندز - سيشيل
Project number
3698
Site inspections
3

Schedule

Between November 2025 and May 2026 the site added about 0.4 points a month. At that rate it would finish around July 2049, more than three months after its registered date of June 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 May 2026

2.5%+2.1 pts

  • Damac Islands - Seychelles 1 construction site, inspection photo 1, 1 May 2026
  • Damac Islands - Seychelles 1 construction site, inspection photo 2, 1 May 2026
  • Damac Islands - Seychelles 1 construction site, inspection photo 3, 1 May 2026

4 November 2025

0.4%+0.4 pts

  • Damac Islands - Seychelles 1 construction site, inspection photo 1, 4 November 2025
  • Damac Islands - Seychelles 1 construction site, inspection photo 2, 4 November 2025
  • Damac Islands - Seychelles 1 construction site, inspection photo 3, 4 November 2025

21 April 2025

0%

  • Damac Islands - Seychelles 1 construction site, inspection photo 1, 21 April 2025
  • Damac Islands - Seychelles 1 construction site, inspection photo 2, 21 April 2025

All 8 site photos, by inspection date

Context

Al Yelayiss 1 has 18 projects under construction, 6.5% built on average.

Damac Elite Investment Co has 20 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Damac Islands - Seychelles 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Islands - Seychelles 1 handover date?
The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2049. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Islands - Seychelles 1?
Damac Islands - Seychelles 1 was 2.5% built at the site inspection on 1 May 2026. The site has been inspected 3 times since April 2025. The Land Department took 8 site photos at its inspections.
Is Damac Islands - Seychelles 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building Damac Islands - Seychelles 1?
The registered developer is Damac Elite Investment Co. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Islands - Seychelles 1?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.