Mas Barsha Residency construction progress
Mas Barsha Residency in Al Barsha First was registered to complete in November 2026 and is still under construction. At the last site inspection, in August 2026, it was 26% built. The developer is M A S Real Estate Development.
26%
Built, at the site inspection of 3 August 2026
0 months past its registered completion date
- Registered completion date
- November 2026
- Finish at recent pace
- March 2030
- Construction started
- November 2024
- First registered
- November 2025
- Developer
- M A S Real Estate Development
- Community
- Al Barsha First
- Units
- 242
- Escrow bank
- Mashreq Bank
- Name in Arabic
- ماس برشا ريزيدينسي
- Project number
- 3399
- Site inspections
- 6
Schedule
Mas Barsha Residency was registered to complete in November 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around March 2030.
Site inspections
3 August 2026
26%+2.5 pts
19 June 2026
24%+7.8 pts
11 November 2025
16%+5.6 pts
23 October 2025
10%+3.9 pts
30 June 2025
6.5%+1.1 pts
13 March 2025
5.4%
Context
Al Barsha First has 2 projects under construction, 59% built on average.
Own a unit in Mas Barsha Residency?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mas Barsha Residency handover date?
- The registered completion date was November 2026, and the register still lists Mas Barsha Residency as under construction. At the pace of its recent inspections the site would reach 100% around March 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mas Barsha Residency?
- Mas Barsha Residency was 26% built at the site inspection on 3 August 2026. The site has been inspected 6 times since March 2025. The Land Department took 31 site photos at its inspections.
- Is Mas Barsha Residency delayed?
- Yes. Its registered completion date of November 2026 has passed and the project is still listed as under construction.
- Who is building Mas Barsha Residency?
- The registered developer is M A S Real Estate Development.
- Which bank holds the escrow account for Mas Barsha Residency?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Api- Barsha Residential TowerNearby in Al Barsha First. 93%, Due October 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.