Mas Barsha Residency construction progress

Mas Barsha Residency in Al Barsha First is 26% built at the Land Department inspection of August 2026. Developer M A S Real Estate Development. Completion registered for November 2026.

26%

Built, at the Land Department site inspection of 3 August 2026

Running behind its date

Completion date (Land Department)
November 2026
Finish at recent pace
March 2030
Construction started
November 2024
Registered with the Land Department
November 2025
Developer
M A S Real Estate Development
Community
Al Barsha First
Units
242
Escrow bank
Mashreq Bank
Name in Arabic
ماس برشا ريزيدينسي
Land Department project number
3399
Land Department site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 1.7 points a month. At that rate it would finish around March 2030, more than three months after the November 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

26%+2.5 pts

  • Mas Barsha Residency construction site, Land Department inspection photo 1, 3 August 2026
  • Mas Barsha Residency construction site, Land Department inspection photo 2, 3 August 2026
  • Mas Barsha Residency construction site, Land Department inspection photo 3, 3 August 2026
  • Mas Barsha Residency construction site, Land Department inspection photo 4, 3 August 2026

19 June 2026

24%+7.8 pts

  • Mas Barsha Residency construction site, Land Department inspection photo 1, 19 June 2026
  • Mas Barsha Residency construction site, Land Department inspection photo 2, 19 June 2026
  • Mas Barsha Residency construction site, Land Department inspection photo 3, 19 June 2026
  • Mas Barsha Residency construction site, Land Department inspection photo 4, 19 June 2026

11 November 2025

16%+5.6 pts

  • Mas Barsha Residency construction site, Land Department inspection photo 1, 11 November 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 2, 11 November 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 3, 11 November 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 4, 11 November 2025

23 October 2025

10%+3.9 pts

  • Mas Barsha Residency construction site, Land Department inspection photo 1, 23 October 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 2, 23 October 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 3, 23 October 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 4, 23 October 2025

30 June 2025

6.5%+1.1 pts

  • Mas Barsha Residency construction site, Land Department inspection photo 1, 30 June 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 2, 30 June 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 3, 30 June 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 4, 30 June 2025

13 March 2025

5.4%

  • Mas Barsha Residency construction site, Land Department inspection photo 1, 13 March 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 2, 13 March 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 3, 13 March 2025
  • Mas Barsha Residency construction site, Land Department inspection photo 4, 13 March 2025

All 31 site photos, by inspection date

Context

Al Barsha First has 2 projects under construction, 59% built on average.

Own a unit in Mas Barsha Residency?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Mas Barsha Residency be completed?
The completion date registered with the Dubai Land Department is November 2026. At the pace of its recent inspections the site would reach 100% around March 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mas Barsha Residency is built?
26%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 6 times since March 2025.
Is Mas Barsha Residency delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2026.
Who is building Mas Barsha Residency?
The registered developer is M A S Real Estate Development.
Which bank holds the escrow account for Mas Barsha Residency?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.