Mas Barsha Residency construction progress

Mas Barsha Residency in Al Barsha First was registered to complete in November 2026 and is still under construction. At the last site inspection, in August 2026, it was 26% built. The developer is M A S Real Estate Development.

26%

Built, at the site inspection of 3 August 2026

0 months past its registered completion date

Registered completion date
November 2026
Finish at recent pace
March 2030
Construction started
November 2024
First registered
November 2025
Developer
M A S Real Estate Development
Community
Al Barsha First
Units
242
Escrow bank
Mashreq Bank
Name in Arabic
ماس برشا ريزيدينسي
Project number
3399
Site inspections
6

Schedule

Mas Barsha Residency was registered to complete in November 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around March 2030.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 August 2026

26%+2.5 pts

  • Mas Barsha Residency construction site, inspection photo 1, 3 August 2026
  • Mas Barsha Residency construction site, inspection photo 2, 3 August 2026
  • Mas Barsha Residency construction site, inspection photo 3, 3 August 2026
  • Mas Barsha Residency construction site, inspection photo 4, 3 August 2026

19 June 2026

24%+7.8 pts

  • Mas Barsha Residency construction site, inspection photo 1, 19 June 2026
  • Mas Barsha Residency construction site, inspection photo 2, 19 June 2026
  • Mas Barsha Residency construction site, inspection photo 3, 19 June 2026
  • Mas Barsha Residency construction site, inspection photo 4, 19 June 2026

11 November 2025

16%+5.6 pts

  • Mas Barsha Residency construction site, inspection photo 1, 11 November 2025
  • Mas Barsha Residency construction site, inspection photo 2, 11 November 2025
  • Mas Barsha Residency construction site, inspection photo 3, 11 November 2025
  • Mas Barsha Residency construction site, inspection photo 4, 11 November 2025

23 October 2025

10%+3.9 pts

  • Mas Barsha Residency construction site, inspection photo 1, 23 October 2025
  • Mas Barsha Residency construction site, inspection photo 2, 23 October 2025
  • Mas Barsha Residency construction site, inspection photo 3, 23 October 2025
  • Mas Barsha Residency construction site, inspection photo 4, 23 October 2025

30 June 2025

6.5%+1.1 pts

  • Mas Barsha Residency construction site, inspection photo 1, 30 June 2025
  • Mas Barsha Residency construction site, inspection photo 2, 30 June 2025
  • Mas Barsha Residency construction site, inspection photo 3, 30 June 2025
  • Mas Barsha Residency construction site, inspection photo 4, 30 June 2025

13 March 2025

5.4%

  • Mas Barsha Residency construction site, inspection photo 1, 13 March 2025
  • Mas Barsha Residency construction site, inspection photo 2, 13 March 2025
  • Mas Barsha Residency construction site, inspection photo 3, 13 March 2025
  • Mas Barsha Residency construction site, inspection photo 4, 13 March 2025

All 31 site photos, by inspection date

Context

Al Barsha First has 2 projects under construction, 59% built on average.

Own a unit in Mas Barsha Residency?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mas Barsha Residency handover date?
The registered completion date was November 2026, and the register still lists Mas Barsha Residency as under construction. At the pace of its recent inspections the site would reach 100% around March 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mas Barsha Residency?
Mas Barsha Residency was 26% built at the site inspection on 3 August 2026. The site has been inspected 6 times since March 2025. The Land Department took 31 site photos at its inspections.
Is Mas Barsha Residency delayed?
Yes. Its registered completion date of November 2026 has passed and the project is still listed as under construction.
Who is building Mas Barsha Residency?
The registered developer is M A S Real Estate Development.
Which bank holds the escrow account for Mas Barsha Residency?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.