South Park Residences By Wellington construction progress

The register lists South Park Residences By Wellington in Saih Shuaib 2 as complete, with a registered completion date of December 2027. Its last site inspection on record was in October 2026. The developer is Wellington Elite Real Estate Development.

100%

Built, at the site inspection of 8 October 2026

Construction complete

Registered completion date
December 2027
Construction started
December 2024
First registered
April 2025
Developer
Wellington Elite Real Estate Development
Community
Saih Shuaib 2
Units
23
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ساوث بارك ريزيدنسز من ويلينغتون
Project number
3453
Site inspections
8

Schedule

The register lists South Park Residences By Wellington as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2026

97%+5.4 pts

  • South Park Residences By Wellington construction site, inspection photo 1, 8 October 2026
  • South Park Residences By Wellington construction site, inspection photo 2, 8 October 2026
  • South Park Residences By Wellington construction site, inspection photo 3, 8 October 2026
  • South Park Residences By Wellington construction site, inspection photo 4, 8 October 2026

20 July 2026

91%+8.8 pts

  • South Park Residences By Wellington construction site, inspection photo 1, 20 July 2026
  • South Park Residences By Wellington construction site, inspection photo 2, 20 July 2026
  • South Park Residences By Wellington construction site, inspection photo 3, 20 July 2026
  • South Park Residences By Wellington construction site, inspection photo 4, 20 July 2026

24 April 2026

82%+13 pts

  • South Park Residences By Wellington construction site, inspection photo 1, 24 April 2026
  • South Park Residences By Wellington construction site, inspection photo 2, 24 April 2026
  • South Park Residences By Wellington construction site, inspection photo 3, 24 April 2026
  • South Park Residences By Wellington construction site, inspection photo 4, 24 April 2026

28 January 2026

69%+19 pts

  • South Park Residences By Wellington construction site, inspection photo 1, 28 January 2026
  • South Park Residences By Wellington construction site, inspection photo 2, 28 January 2026
  • South Park Residences By Wellington construction site, inspection photo 3, 28 January 2026
  • South Park Residences By Wellington construction site, inspection photo 4, 28 January 2026

9 October 2025

50%+25 pts

  • South Park Residences By Wellington construction site, inspection photo 1, 9 October 2025
  • South Park Residences By Wellington construction site, inspection photo 2, 9 October 2025
  • South Park Residences By Wellington construction site, inspection photo 3, 9 October 2025
  • South Park Residences By Wellington construction site, inspection photo 4, 9 October 2025

22 July 2025

25%+3.7 pts

  • South Park Residences By Wellington construction site, inspection photo 1, 22 July 2025
  • South Park Residences By Wellington construction site, inspection photo 2, 22 July 2025
  • South Park Residences By Wellington construction site, inspection photo 3, 22 July 2025
  • South Park Residences By Wellington construction site, inspection photo 4, 22 July 2025

20 May 2025

21%+19 pts

  • South Park Residences By Wellington construction site, inspection photo 1, 20 May 2025
  • South Park Residences By Wellington construction site, inspection photo 2, 20 May 2025
  • South Park Residences By Wellington construction site, inspection photo 3, 20 May 2025
  • South Park Residences By Wellington construction site, inspection photo 4, 20 May 2025

5 February 2025

3.0%

  • South Park Residences By Wellington construction site, inspection photo 1, 5 February 2025
  • South Park Residences By Wellington construction site, inspection photo 2, 5 February 2025
  • South Park Residences By Wellington construction site, inspection photo 3, 5 February 2025
  • South Park Residences By Wellington construction site, inspection photo 4, 5 February 2025

All 55 site photos, by inspection date

Context

Saih Shuaib 2 has 6 projects under construction, 26% built on average.

Own a unit in South Park Residences By Wellington?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the South Park Residences By Wellington handover date?
Construction of South Park Residences By Wellington is recorded as complete, with a registered completion date of December 2027. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on South Park Residences By Wellington?
South Park Residences By Wellington was 100% built at the site inspection on 8 October 2026. The site has been inspected 8 times since February 2025. The Land Department took 55 site photos at its inspections.
Is South Park Residences By Wellington delayed?
The register lists construction as complete.
Who is building South Park Residences By Wellington?
The registered developer is Wellington Elite Real Estate Development.
Which bank holds the escrow account for South Park Residences By Wellington?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.