Nad Al Sheba Gardens Phase 3 construction progress

Nad Al Sheba Gardens Phase 3 in Nad Al Sheba Gardens is 97% built at the Land Department inspection of July 2026. Developer Al Qudra Estates. Completion registered for April 2026.

97%

Built, at the Land Department site inspection of 30 July 2026

6 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
September 2026
Construction started
January 2023
Registered with the Land Department
October 2022
Developer
Al Qudra Estates
Units
235
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ند الشبا جاردنز المرحله الثالثه
Land Department project number
2484
Land Department site inspections
9

Schedule

Nad Al Sheba Gardens Phase 3 was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.5 points a month. Kept at that rate, the site would reach 100% around September 2026.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 July 2026

97%+1.3 pts

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 30 July 2026
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 30 July 2026
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 30 July 2026
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 4, 30 July 2026

24 March 2026

96%+15 pts

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 24 March 2026
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 24 March 2026
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 24 March 2026
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 4, 24 March 2026

3 December 2025

80%+11 pts

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 3 December 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 3 December 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 3 December 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 4, 3 December 2025

25 August 2025

70%+20 pts

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 25 August 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 25 August 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 25 August 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 4, 25 August 2025

9 June 2025

50%+18 pts

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 9 June 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 9 June 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 9 June 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 4, 9 June 2025

28 February 2025

32%+31 pts

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 28 February 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 28 February 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 28 February 2025
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 4, 28 February 2025

31 May 2024

1.1%+0.6 pts

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 31 May 2024
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 31 May 2024
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 31 May 2024

18 July 2023

0.5%+0.5 pts

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 18 July 2023
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 18 July 2023
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 18 July 2023
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 4, 18 July 2023

12 October 2022

0%

  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 1, 12 October 2022
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 2, 12 October 2022
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 3, 12 October 2022
  • Nad Al Sheba Gardens Phase 3 construction site, Land Department inspection photo 4, 12 October 2022

All 64 site photos, by inspection date

Context

Nad Al Sheba Gardens has 9 projects under construction, 52% built on average.

Own a unit in Nad Al Sheba Gardens Phase 3?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Nad Al Sheba Gardens Phase 3 be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Nad Al Sheba Gardens Phase 3 is built?
97%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 9 times since October 2022.
Is Nad Al Sheba Gardens Phase 3 delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Nad Al Sheba Gardens Phase 3?
The registered developer is Al Qudra Estates.
Which bank holds the escrow account for Nad Al Sheba Gardens Phase 3?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.