Nad Al Sheba Gardens Phase 3 construction progress
Nad Al Sheba Gardens Phase 3 in Nad Al Sheba Gardens is 97% built at the Land Department inspection of July 2026. Developer Al Qudra Estates. Completion registered for April 2026.
97%
Built, at the Land Department site inspection of 30 July 2026
6 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- September 2026
- Construction started
- January 2023
- Registered with the Land Department
- October 2022
- Developer
- Al Qudra Estates
- Community
- Nad Al Sheba Gardens
- Units
- 235
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- ند الشبا جاردنز المرحله الثالثه
- Land Department project number
- 2484
- Land Department site inspections
- 9
Schedule
Nad Al Sheba Gardens Phase 3 was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.5 points a month. Kept at that rate, the site would reach 100% around September 2026.
Site inspections
30 July 2026
97%+1.3 pts
24 March 2026
96%+15 pts
3 December 2025
80%+11 pts
25 August 2025
70%+20 pts
9 June 2025
50%+18 pts
28 February 2025
32%+31 pts
31 May 2024
1.1%+0.6 pts
18 July 2023
0.5%+0.5 pts
12 October 2022
0%
Context
Nad Al Sheba Gardens has 9 projects under construction, 52% built on average.
Own a unit in Nad Al Sheba Gardens Phase 3?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Nad Al Sheba Gardens Phase 3 be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Nad Al Sheba Gardens Phase 3 is built?
- 97%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 9 times since October 2022.
- Is Nad Al Sheba Gardens Phase 3 delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Nad Al Sheba Gardens Phase 3?
- The registered developer is Al Qudra Estates.
- Which bank holds the escrow account for Nad Al Sheba Gardens Phase 3?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nad Al Sheba Gardens Phase 4Nearby in Nad Al Sheba Gardens. 57%.
- Nad Al Sheba Gardens Phase 5Nearby in Nad Al Sheba Gardens. 38%.
- Nad Al Sheba Gardens Phase 6Nearby in Nad Al Sheba Gardens. 14%.
- One By NineNearby in Nad Al Sheba Gardens. 50%, Due November 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)