One By Nine construction progress
One By Nine in Nad Al Sheba Gardens was registered to complete in November 2025 and is still under construction. At the last site inspection, in June 2026, it was 50% built. The developer is Nine Asset Developments.
50%
Built, at the site inspection of 11 June 2026
13 months past its registered completion date
- Registered completion date
- November 2025
- Finish at recent pace
- November 2027
- Construction started
- May 2024
- First registered
- September 2024
- Developer
- Nine Asset Developments
- Community
- Nad Al Sheba Gardens
- Units
- 46
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ون باي نائن
- Project number
- 3099
- Site inspections
- 5
Schedule
One By Nine was registered to complete in November 2025, 13 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around November 2027.
Site inspections
11 June 2026
50%+12 pts
9 April 2026
39%+18 pts
31 July 2025
20%+10 pts
5 March 2025
10%+10 pts
31 July 2024
0%
Context
Nad Al Sheba Gardens has 8 projects under construction, 52% built on average.
Own a unit in One By Nine?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the One By Nine handover date?
- The registered completion date was November 2025, and the register still lists One By Nine as under construction. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on One By Nine?
- One By Nine was 50% built at the site inspection on 11 June 2026. The site has been inspected 5 times since July 2024. The Land Department took 35 site photos at its inspections.
- Is One By Nine delayed?
- Yes. Its registered completion date of November 2025 has passed and the project is still listed as under construction.
- Who is building One By Nine?
- The registered developer is Nine Asset Developments.
- Which bank holds the escrow account for One By Nine?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nad Al Sheba Gardens Phase 3Nearby in Nad Al Sheba Gardens. 97%, Due April 2026, passed.
- Nad Al Sheba Gardens Phase 4Nearby in Nad Al Sheba Gardens. 76%.
- Nad Al Sheba Gardens Phase 5Nearby in Nad Al Sheba Gardens. 38%.
- Nad Al Sheba Gardens Phase 6Nearby in Nad Al Sheba Gardens. 14%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.