Skip to content

One By Nine construction progress

One By Nine in Nad Al Sheba Gardens was registered to complete in November 2025 and is still under construction. At the last site inspection, in June 2026, it was 50% built. The developer is Nine Asset Developments.

50%

Built, at the site inspection of 11 June 2026

13 months past its registered completion date

Registered completion date
November 2025
Finish at recent pace
November 2027
Construction started
May 2024
First registered
September 2024
Developer
Nine Asset Developments
Units
46
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ون باي نائن
Project number
3099
Site inspections
5

Schedule

One By Nine was registered to complete in November 2025, 13 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around November 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 June 2026

50%+12 pts

  • One By Nine construction site, inspection photo 1, 11 June 2026
  • One By Nine construction site, inspection photo 2, 11 June 2026
  • One By Nine construction site, inspection photo 3, 11 June 2026
  • One By Nine construction site, inspection photo 4, 11 June 2026

9 April 2026

39%+18 pts

  • One By Nine construction site, inspection photo 1, 9 April 2026
  • One By Nine construction site, inspection photo 2, 9 April 2026
  • One By Nine construction site, inspection photo 3, 9 April 2026
  • One By Nine construction site, inspection photo 4, 9 April 2026

31 July 2025

20%+10 pts

  • One By Nine construction site, inspection photo 1, 31 July 2025
  • One By Nine construction site, inspection photo 2, 31 July 2025
  • One By Nine construction site, inspection photo 3, 31 July 2025
  • One By Nine construction site, inspection photo 4, 31 July 2025

5 March 2025

10%+10 pts

  • One By Nine construction site, inspection photo 1, 5 March 2025
  • One By Nine construction site, inspection photo 2, 5 March 2025
  • One By Nine construction site, inspection photo 3, 5 March 2025
  • One By Nine construction site, inspection photo 4, 5 March 2025

31 July 2024

0%

  • One By Nine construction site, inspection photo 1, 31 July 2024
  • One By Nine construction site, inspection photo 2, 31 July 2024

All 35 site photos, by inspection date

Context

Nad Al Sheba Gardens has 8 projects under construction, 52% built on average.

Own a unit in One By Nine?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the One By Nine handover date?
The registered completion date was November 2025, and the register still lists One By Nine as under construction. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on One By Nine?
One By Nine was 50% built at the site inspection on 11 June 2026. The site has been inspected 5 times since July 2024. The Land Department took 35 site photos at its inspections.
Is One By Nine delayed?
Yes. Its registered completion date of November 2025 has passed and the project is still listed as under construction.
Who is building One By Nine?
The registered developer is Nine Asset Developments.
Which bank holds the escrow account for One By Nine?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.