One By Nine construction progress
One By Nine in Nad Al Sheba Gardens is 50% built at the Land Department inspection of June 2026. Developer Nine Asset Developments. Completion registered for November 2025.
50%
Built, at the Land Department site inspection of 11 June 2026
11 months past its registered completion date
- Completion date (Land Department)
- November 2025
- Finish at recent pace
- November 2027
- Construction started
- May 2024
- Registered with the Land Department
- September 2024
- Developer
- Nine Asset Developments
- Community
- Nad Al Sheba Gardens
- Units
- 46
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ون باي نائن
- Land Department project number
- 3099
- Land Department site inspections
- 5
Schedule
One By Nine was registered to complete in November 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around November 2027.
Site inspections
11 June 2026
50%+12 pts
9 April 2026
39%+18 pts
31 July 2025
20%+10 pts
5 March 2025
10%+10 pts
31 July 2024
0%
Context
Nad Al Sheba Gardens has 9 projects under construction, 52% built on average.
Own a unit in One By Nine?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will One By Nine be completed?
- The completion date registered with the Dubai Land Department is November 2025. At the pace of its recent inspections the site would reach 100% around November 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of One By Nine is built?
- 50%, measured at the Land Department site inspection on 11 June 2026. The Land Department engineers have inspected the site 5 times since July 2024.
- Is One By Nine delayed?
- Yes. Its registered completion date of November 2025 has passed and the Land Department still lists it as under construction.
- Who is building One By Nine?
- The registered developer is Nine Asset Developments.
- Which bank holds the escrow account for One By Nine?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nad Al Sheba Gardens Phase 3Nearby in Nad Al Sheba Gardens. 97%, Due April 2026, passed.
- Nad Al Sheba Gardens Phase 4Nearby in Nad Al Sheba Gardens. 57%.
- Nad Al Sheba Gardens Phase 5Nearby in Nad Al Sheba Gardens. 38%.
- Nad Al Sheba Gardens Phase 6Nearby in Nad Al Sheba Gardens. 14%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.