One By Nine construction progress

One By Nine in Nad Al Sheba Gardens is 50% built at the Land Department inspection of June 2026. Developer Nine Asset Developments. Completion registered for November 2025.

50%

Built, at the Land Department site inspection of 11 June 2026

11 months past its registered completion date

Completion date (Land Department)
November 2025
Finish at recent pace
November 2027
Construction started
May 2024
Registered with the Land Department
September 2024
Developer
Nine Asset Developments
Units
46
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ون باي نائن
Land Department project number
3099
Land Department site inspections
5

Schedule

One By Nine was registered to complete in November 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around November 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

11 June 2026

50%+12 pts

  • One By Nine construction site, Land Department inspection photo 1, 11 June 2026
  • One By Nine construction site, Land Department inspection photo 2, 11 June 2026
  • One By Nine construction site, Land Department inspection photo 3, 11 June 2026
  • One By Nine construction site, Land Department inspection photo 4, 11 June 2026

9 April 2026

39%+18 pts

  • One By Nine construction site, Land Department inspection photo 1, 9 April 2026
  • One By Nine construction site, Land Department inspection photo 2, 9 April 2026
  • One By Nine construction site, Land Department inspection photo 3, 9 April 2026
  • One By Nine construction site, Land Department inspection photo 4, 9 April 2026

31 July 2025

20%+10 pts

  • One By Nine construction site, Land Department inspection photo 1, 31 July 2025
  • One By Nine construction site, Land Department inspection photo 2, 31 July 2025
  • One By Nine construction site, Land Department inspection photo 3, 31 July 2025
  • One By Nine construction site, Land Department inspection photo 4, 31 July 2025

5 March 2025

10%+10 pts

  • One By Nine construction site, Land Department inspection photo 1, 5 March 2025
  • One By Nine construction site, Land Department inspection photo 2, 5 March 2025
  • One By Nine construction site, Land Department inspection photo 3, 5 March 2025
  • One By Nine construction site, Land Department inspection photo 4, 5 March 2025

31 July 2024

0%

  • One By Nine construction site, Land Department inspection photo 1, 31 July 2024
  • One By Nine construction site, Land Department inspection photo 2, 31 July 2024

All 35 site photos, by inspection date

Context

Nad Al Sheba Gardens has 9 projects under construction, 52% built on average.

Own a unit in One By Nine?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will One By Nine be completed?
The completion date registered with the Dubai Land Department is November 2025. At the pace of its recent inspections the site would reach 100% around November 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of One By Nine is built?
50%, measured at the Land Department site inspection on 11 June 2026. The Land Department engineers have inspected the site 5 times since July 2024.
Is One By Nine delayed?
Yes. Its registered completion date of November 2025 has passed and the Land Department still lists it as under construction.
Who is building One By Nine?
The registered developer is Nine Asset Developments.
Which bank holds the escrow account for One By Nine?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.