Nad Al Sheba Gardens Phase 3 construction photos
64 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Nad Al Sheba Gardens Phase 3 was built on the day of each visit.
30 July 202697% built
24 March 202696% built
3 December 202580% built
25 August 202570% built
9 June 202550% built
28 February 202532% built
31 May 20241.1% built
18 July 20230.5% built
12 October 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.