Lagoon Views At District One construction progress

The register lists Lagoon Views At District One in Mohammed Bin Rashid Al Maktoum City -District -1 Community as complete, with a registered completion date of March 2025. Its last site inspection on record was in May 2025. The developer is District One.

100%

Built, at the site inspection of 8 May 2025

Construction complete

Registered completion date
March 2025
Construction started
April 2022
First registered
November 2021
Developer
District One
Community
Mohammed Bin Rashid Al Maktoum City -District -1 Community
Units
104
Escrow bank
Dubai Islamic Bank
Name in Arabic
لاجون فيوز في ديستريكت ون
Project number
2310
Site inspections
10

Schedule

The register lists Lagoon Views At District One as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 May 2025

100%+9.7 pts

  • Lagoon Views At District One construction site, inspection photo 1, 8 May 2025
  • Lagoon Views At District One construction site, inspection photo 2, 8 May 2025
  • Lagoon Views At District One construction site, inspection photo 3, 8 May 2025
  • Lagoon Views At District One construction site, inspection photo 4, 8 May 2025

31 January 2025

90%+37 pts

  • Lagoon Views At District One construction site, inspection photo 1, 31 January 2025
  • Lagoon Views At District One construction site, inspection photo 2, 31 January 2025
  • Lagoon Views At District One construction site, inspection photo 3, 31 January 2025
  • Lagoon Views At District One construction site, inspection photo 4, 31 January 2025

20 June 2024

53%+5.1 pts

  • Lagoon Views At District One construction site, inspection photo 1, 20 June 2024
  • Lagoon Views At District One construction site, inspection photo 2, 20 June 2024
  • Lagoon Views At District One construction site, inspection photo 3, 20 June 2024
  • Lagoon Views At District One construction site, inspection photo 4, 20 June 2024

6 May 2024

48%+17 pts

  • Lagoon Views At District One construction site, inspection photo 1, 6 May 2024
  • Lagoon Views At District One construction site, inspection photo 2, 6 May 2024
  • Lagoon Views At District One construction site, inspection photo 3, 6 May 2024
  • Lagoon Views At District One construction site, inspection photo 4, 6 May 2024

14 December 2023

31%+11 pts

  • Lagoon Views At District One construction site, inspection photo 1, 14 December 2023
  • Lagoon Views At District One construction site, inspection photo 2, 14 December 2023
  • Lagoon Views At District One construction site, inspection photo 3, 14 December 2023
  • Lagoon Views At District One construction site, inspection photo 4, 14 December 2023

18 September 2023

21%+8.9 pts

  • Lagoon Views At District One construction site, inspection photo 1, 18 September 2023
  • Lagoon Views At District One construction site, inspection photo 2, 18 September 2023
  • Lagoon Views At District One construction site, inspection photo 3, 18 September 2023
  • Lagoon Views At District One construction site, inspection photo 4, 18 September 2023

13 June 2023

12%+8.7 pts

  • Lagoon Views At District One construction site, inspection photo 1, 13 June 2023
  • Lagoon Views At District One construction site, inspection photo 2, 13 June 2023
  • Lagoon Views At District One construction site, inspection photo 3, 13 June 2023

31 January 2023

3.0%+2.8 pts

  • Lagoon Views At District One construction site, inspection photo 1, 31 January 2023
  • Lagoon Views At District One construction site, inspection photo 2, 31 January 2023
  • Lagoon Views At District One construction site, inspection photo 3, 31 January 2023

9 November 2022

0.2%+0.2 pts

  • Lagoon Views At District One construction site, inspection photo 1, 9 November 2022
  • Lagoon Views At District One construction site, inspection photo 2, 9 November 2022
  • Lagoon Views At District One construction site, inspection photo 3, 9 November 2022

29 July 2022

0%

  • Lagoon Views At District One construction site, inspection photo 1, 29 July 2022
  • Lagoon Views At District One construction site, inspection photo 2, 29 July 2022
  • Lagoon Views At District One construction site, inspection photo 3, 29 July 2022

All 64 site photos, by inspection date

Context

District One has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Lagoon Views At District One?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Lagoon Views At District One handover date?
Construction of Lagoon Views At District One is recorded as complete, with a registered completion date of March 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Lagoon Views At District One?
Lagoon Views At District One was 100% built at the site inspection on 8 May 2025. The site has been inspected 10 times since July 2022. The Land Department took 64 site photos at its inspections.
Is Lagoon Views At District One delayed?
The register lists construction as complete.
Who is building Lagoon Views At District One?
The registered developer is District One. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Lagoon Views At District One?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.