Lagoon Views At District One construction photos

64 photos from 10 site inspections, newest first. The percentage is how much of Lagoon Views At District One was built on the day of each visit.

8 May 2025100% built

31 January 202590% built

20 June 202453% built

6 May 202448% built

14 December 202331% built

18 September 202321% built

13 June 202312% built

31 January 20233.0% built

9 November 20220.2% built

29 July 20220% built

Back to Lagoon Views At District One construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.