Naya At District One construction progress

The registered completion date for Naya At District One in Mohammed Bin Rashid Al Maktoum City -District -1 Community is September 2027. At the last site inspection, in October 2026, it was 68% built. The developer is District One.

68%

Built, at the site inspection of 27 October 2026

On pace for its date

Registered completion date
September 2027
Finish at recent pace
June 2027
Construction started
October 2023
First registered
June 2023
Developer
District One
Community
Mohammed Bin Rashid Al Maktoum City -District -1 Community
Units
456
Escrow bank
Dubai Islamic Bank
Name in Arabic
نايا في ديستريكت ون
Project number
2674
Site inspections
9

Schedule

Since January 2026 Naya At District One has added about 4.4 points a month. That puts 100% around June 2027, within three months of its registered completion date of September 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

68%+12 pts

  • Naya At District One construction site, inspection photo 1, 27 October 2026
  • Naya At District One construction site, inspection photo 2, 27 October 2026
  • Naya At District One construction site, inspection photo 3, 27 October 2026
  • Naya At District One construction site, inspection photo 4, 27 October 2026

22 July 2026

56%+19 pts

  • Naya At District One construction site, inspection photo 1, 22 July 2026
  • Naya At District One construction site, inspection photo 2, 22 July 2026
  • Naya At District One construction site, inspection photo 3, 22 July 2026
  • Naya At District One construction site, inspection photo 4, 22 July 2026

28 April 2026

37%+11 pts

  • Naya At District One construction site, inspection photo 1, 28 April 2026
  • Naya At District One construction site, inspection photo 2, 28 April 2026
  • Naya At District One construction site, inspection photo 3, 28 April 2026
  • Naya At District One construction site, inspection photo 4, 28 April 2026

6 January 2026

26%+19 pts

  • Naya At District One construction site, inspection photo 1, 6 January 2026
  • Naya At District One construction site, inspection photo 2, 6 January 2026
  • Naya At District One construction site, inspection photo 3, 6 January 2026
  • Naya At District One construction site, inspection photo 4, 6 January 2026

23 September 2025

6.8%+4.4 pts

  • Naya At District One construction site, inspection photo 1, 23 September 2025
  • Naya At District One construction site, inspection photo 2, 23 September 2025
  • Naya At District One construction site, inspection photo 3, 23 September 2025
  • Naya At District One construction site, inspection photo 4, 23 September 2025

11 June 2025

2.3%+2.1 pts

  • Naya At District One construction site, inspection photo 1, 11 June 2025
  • Naya At District One construction site, inspection photo 2, 11 June 2025
  • Naya At District One construction site, inspection photo 3, 11 June 2025
  • Naya At District One construction site, inspection photo 4, 11 June 2025

19 March 2025

0.2%+0.2 pts

  • Naya At District One construction site, inspection photo 1, 19 March 2025
  • Naya At District One construction site, inspection photo 2, 19 March 2025
  • Naya At District One construction site, inspection photo 3, 19 March 2025

18 December 2024

0%

  • Naya At District One construction site, inspection photo 1, 18 December 2024
  • Naya At District One construction site, inspection photo 2, 18 December 2024
  • Naya At District One construction site, inspection photo 3, 18 December 2024

29 May 2023

0%

  • Naya At District One construction site, inspection photo 1, 29 May 2023

All 55 site photos, by inspection date

Context

Own a unit in Naya At District One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Naya At District One handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Naya At District One?
Naya At District One was 68% built at the site inspection on 27 October 2026. The site has been inspected 9 times since May 2023. The Land Department took 55 site photos at its inspections.
Is Naya At District One delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of September 2027.
Who is building Naya At District One?
The registered developer is District One.
Which bank holds the escrow account for Naya At District One?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.