Naya At District One construction progress

Naya At District One in Mohammed Bin Rashid Al Maktoum City -District -1 Community is 56% built at the Land Department inspection of July 2026. Developer District One. Completion registered for September 2027.

56%

Built, at the Land Department site inspection of 22 July 2026

On pace for its date

Completion date (Land Department)
September 2027
Finish at recent pace
April 2027
Construction started
October 2023
Registered with the Land Department
June 2023
Developer
District One
Community
Mohammed Bin Rashid Al Maktoum City -District -1 Community
Units
456
Escrow bank
Dubai Islamic Bank
Name in Arabic
نايا في ديستريكت ون
Land Department project number
2674
Land Department site inspections
8

Schedule

Since September 2025 Naya At District One has added about 5.0 points a month. That puts 100% around April 2027, within three months of its registered completion date of September 2027.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 July 2026

56%+19 pts

  • Naya At District One construction site, Land Department inspection photo 1, 22 July 2026
  • Naya At District One construction site, Land Department inspection photo 2, 22 July 2026
  • Naya At District One construction site, Land Department inspection photo 3, 22 July 2026
  • Naya At District One construction site, Land Department inspection photo 4, 22 July 2026

28 April 2026

37%+11 pts

  • Naya At District One construction site, Land Department inspection photo 1, 28 April 2026
  • Naya At District One construction site, Land Department inspection photo 2, 28 April 2026
  • Naya At District One construction site, Land Department inspection photo 3, 28 April 2026
  • Naya At District One construction site, Land Department inspection photo 4, 28 April 2026

6 January 2026

26%+19 pts

  • Naya At District One construction site, Land Department inspection photo 1, 6 January 2026
  • Naya At District One construction site, Land Department inspection photo 2, 6 January 2026
  • Naya At District One construction site, Land Department inspection photo 3, 6 January 2026
  • Naya At District One construction site, Land Department inspection photo 4, 6 January 2026

23 September 2025

6.8%+4.4 pts

  • Naya At District One construction site, Land Department inspection photo 1, 23 September 2025
  • Naya At District One construction site, Land Department inspection photo 2, 23 September 2025
  • Naya At District One construction site, Land Department inspection photo 3, 23 September 2025
  • Naya At District One construction site, Land Department inspection photo 4, 23 September 2025

11 June 2025

2.3%+2.1 pts

  • Naya At District One construction site, Land Department inspection photo 1, 11 June 2025
  • Naya At District One construction site, Land Department inspection photo 2, 11 June 2025
  • Naya At District One construction site, Land Department inspection photo 3, 11 June 2025
  • Naya At District One construction site, Land Department inspection photo 4, 11 June 2025

19 March 2025

0.2%+0.2 pts

  • Naya At District One construction site, Land Department inspection photo 1, 19 March 2025
  • Naya At District One construction site, Land Department inspection photo 2, 19 March 2025
  • Naya At District One construction site, Land Department inspection photo 3, 19 March 2025

18 December 2024

0%

  • Naya At District One construction site, Land Department inspection photo 1, 18 December 2024
  • Naya At District One construction site, Land Department inspection photo 2, 18 December 2024
  • Naya At District One construction site, Land Department inspection photo 3, 18 December 2024

29 May 2023

0%

  • Naya At District One construction site, Land Department inspection photo 1, 29 May 2023

All 42 site photos, by inspection date

Context

Own a unit in Naya At District One?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Naya At District One be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around April 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Naya At District One is built?
56%, measured at the Land Department site inspection on 22 July 2026. The Land Department engineers have inspected the site 8 times since May 2023.
Is Naya At District One delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of September 2027.
Who is building Naya At District One?
The registered developer is District One.
Which bank holds the escrow account for Naya At District One?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.