Naya At District One construction progress
The registered completion date for Naya At District One in Mohammed Bin Rashid Al Maktoum City -District -1 Community is September 2027. At the last site inspection, in October 2026, it was 68% built. The developer is District One.
68%
Built, at the site inspection of 27 October 2026
On pace for its date
- Registered completion date
- September 2027
- Finish at recent pace
- June 2027
- Construction started
- October 2023
- First registered
- June 2023
- Developer
- District One
- Community
- Mohammed Bin Rashid Al Maktoum City -District -1 Community
- Units
- 456
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- نايا في ديستريكت ون
- Project number
- 2674
- Site inspections
- 9
Schedule
Since January 2026 Naya At District One has added about 4.4 points a month. That puts 100% around June 2027, within three months of its registered completion date of September 2027.
Site inspections
27 October 2026
68%+12 pts
22 July 2026
56%+19 pts
28 April 2026
37%+11 pts
6 January 2026
26%+19 pts
23 September 2025
6.8%+4.4 pts
11 June 2025
2.3%+2.1 pts
19 March 2025
0.2%+0.2 pts
18 December 2024
0%
29 May 2023
0%
Context
Own a unit in Naya At District One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Naya At District One handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Naya At District One?
- Naya At District One was 68% built at the site inspection on 27 October 2026. The site has been inspected 9 times since May 2023. The Land Department took 55 site photos at its inspections.
- Is Naya At District One delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of September 2027.
- Who is building Naya At District One?
- The registered developer is District One.
- Which bank holds the escrow account for Naya At District One?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



