Sera 1 construction progress
The registered completion date for Sera 1 in Mina Rashid is November 2029. At the last site inspection, in June 2026, it was 0% built. The developer is Mina Rashid Properties.
0%
Built, at the site inspection of 2 June 2026
Running behind its date
- Registered completion date
- November 2029
- Finish at recent pace
- February 4031
- Construction started
- February 2026
- First registered
- August 2025
- Developer
- Mina Rashid Properties
- Community
- Mina Rashid
- Units
- 203
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- سيرا 1
- Project number
- 4031
- Site inspections
- 2
Schedule
Between August 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around February 4031, more than three months after its registered date of November 2029.
Site inspections
2 June 2026
0%+0.0 pts
13 August 2025
0%
Context
Mina Rashid has 18 projects under construction, 21% built on average.
Mina Rashid Properties has 20 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Sera 1?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sera 1 handover date?
- The registered completion date is November 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 4031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sera 1?
- Sera 1 was 0% built at the site inspection on 2 June 2026. The site has been inspected 2 times since August 2025. The Land Department took 4 site photos at its inspections.
- Is Sera 1 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2029.
- Who is building Sera 1?
- The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
- Which bank holds the escrow account for Sera 1?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SeascapeAlso by Mina Rashid Properties. 79%, Due November 2026.
- ClearpointAlso by Mina Rashid Properties. 45%.
- BaylineAlso by Mina Rashid Properties. 61%.
- AvonleaAlso by Mina Rashid Properties. 64%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.



