Clearpoint construction progress

No completion date is registered for Clearpoint in Mina Rashid yet. At the last site inspection, in April 2026, it was 45% built. The developer is Mina Rashid Properties.

45%

Built, at the site inspection of 21 April 2026

Finish at recent pace
December 2027
Construction started
November 2023
First registered
September 2023
Community
Mina Rashid
Units
478
Escrow bank
Emirates NBD
Name in Arabic
كليربوينت
Project number
2743
Site inspections
7

Schedule

Since July 2025 Clearpoint has added about 2.7 points a month. At that rate the site reaches 100% around December 2027. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

21 April 2026

45%+13 pts

  • Clearpoint construction site, inspection photo 1, 21 April 2026
  • Clearpoint construction site, inspection photo 2, 21 April 2026
  • Clearpoint construction site, inspection photo 3, 21 April 2026
  • Clearpoint construction site, inspection photo 4, 21 April 2026

24 November 2025

32%+14 pts

  • Clearpoint construction site, inspection photo 1, 24 November 2025
  • Clearpoint construction site, inspection photo 2, 24 November 2025
  • Clearpoint construction site, inspection photo 3, 24 November 2025
  • Clearpoint construction site, inspection photo 4, 24 November 2025

3 July 2025

19%+8.3 pts

  • Clearpoint construction site, inspection photo 1, 3 July 2025
  • Clearpoint construction site, inspection photo 2, 3 July 2025
  • Clearpoint construction site, inspection photo 3, 3 July 2025
  • Clearpoint construction site, inspection photo 4, 3 July 2025

24 February 2025

10%+4.8 pts

  • Clearpoint construction site, inspection photo 1, 24 February 2025
  • Clearpoint construction site, inspection photo 2, 24 February 2025
  • Clearpoint construction site, inspection photo 3, 24 February 2025
  • Clearpoint construction site, inspection photo 4, 24 February 2025

7 November 2024

5.6%+4.2 pts

  • Clearpoint construction site, inspection photo 1, 7 November 2024
  • Clearpoint construction site, inspection photo 2, 7 November 2024
  • Clearpoint construction site, inspection photo 3, 7 November 2024
  • Clearpoint construction site, inspection photo 4, 7 November 2024

10 May 2024

1.4%+1.4 pts

  • Clearpoint construction site, inspection photo 1, 10 May 2024
  • Clearpoint construction site, inspection photo 2, 10 May 2024
  • Clearpoint construction site, inspection photo 3, 10 May 2024
  • Clearpoint construction site, inspection photo 4, 10 May 2024

8 August 2023

0%

  • Clearpoint construction site, inspection photo 1, 8 August 2023
  • Clearpoint construction site, inspection photo 2, 8 August 2023
  • Clearpoint construction site, inspection photo 3, 8 August 2023

All 36 site photos, by inspection date

Context

Mina Rashid has 18 projects under construction, 21% built on average.

Mina Rashid Properties has 20 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Clearpoint?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Clearpoint handover date?
No completion date is on record for Clearpoint yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Clearpoint?
Clearpoint was 45% built at the site inspection on 21 April 2026. The site has been inspected 7 times since August 2023. The Land Department took 36 site photos at its inspections.
Who is building Clearpoint?
The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Clearpoint?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.