Clearpoint construction progress
Clearpoint in Mina Rashid is 45% built at the Land Department inspection of April 2026. Developer Mina Rashid Properties.
45%
Built, at the Land Department site inspection of 21 April 2026
- Finish at recent pace
- December 2027
- Construction started
- November 2023
- Registered with the Land Department
- September 2023
- Developer
- Mina Rashid Properties
- Community
- Mina Rashid
- Units
- 478
- Escrow bank
- Emirates NBD
- Name in Arabic
- كليربوينت
- Land Department project number
- 2743
- Land Department site inspections
- 7
Schedule
Since July 2025 Clearpoint has added about 2.7 points a month. At that rate the site reaches 100% around December 2027. The Land Department has no completion date on record to compare it with.
Site inspections
21 April 2026
45%+13 pts
24 November 2025
32%+14 pts
3 July 2025
19%+8.3 pts
24 February 2025
10%+4.8 pts
7 November 2024
5.6%+4.2 pts
10 May 2024
1.4%+1.4 pts
8 August 2023
0%
Context
Mina Rashid has 18 projects under construction, 21% built on average.
Mina Rashid Properties has 20 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Clearpoint?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Clearpoint be completed?
- The Land Department has no completion date on record for Clearpoint yet.
- How much of Clearpoint is built?
- 45%, measured at the Land Department site inspection on 21 April 2026. The Land Department engineers have inspected the site 7 times since August 2023.
- Who is building Clearpoint?
- The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
- Which bank holds the escrow account for Clearpoint?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SeascapeAlso by Mina Rashid Properties. 79%, Due November 2026.
- BaylineAlso by Mina Rashid Properties. 61%.
- AvonleaAlso by Mina Rashid Properties. 64%.
- Ocean PointAlso by Mina Rashid Properties. 27%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)