Clearpoint construction progress

Clearpoint in Mina Rashid is 45% built at the Land Department inspection of April 2026. Developer Mina Rashid Properties.

45%

Built, at the Land Department site inspection of 21 April 2026

Finish at recent pace
December 2027
Construction started
November 2023
Registered with the Land Department
September 2023
Community
Mina Rashid
Units
478
Escrow bank
Emirates NBD
Name in Arabic
كليربوينت
Land Department project number
2743
Land Department site inspections
7

Schedule

Since July 2025 Clearpoint has added about 2.7 points a month. At that rate the site reaches 100% around December 2027. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

21 April 2026

45%+13 pts

  • Clearpoint construction site, Land Department inspection photo 1, 21 April 2026
  • Clearpoint construction site, Land Department inspection photo 2, 21 April 2026
  • Clearpoint construction site, Land Department inspection photo 3, 21 April 2026
  • Clearpoint construction site, Land Department inspection photo 4, 21 April 2026

24 November 2025

32%+14 pts

  • Clearpoint construction site, Land Department inspection photo 1, 24 November 2025
  • Clearpoint construction site, Land Department inspection photo 2, 24 November 2025
  • Clearpoint construction site, Land Department inspection photo 3, 24 November 2025
  • Clearpoint construction site, Land Department inspection photo 4, 24 November 2025

3 July 2025

19%+8.3 pts

  • Clearpoint construction site, Land Department inspection photo 1, 3 July 2025
  • Clearpoint construction site, Land Department inspection photo 2, 3 July 2025
  • Clearpoint construction site, Land Department inspection photo 3, 3 July 2025
  • Clearpoint construction site, Land Department inspection photo 4, 3 July 2025

24 February 2025

10%+4.8 pts

  • Clearpoint construction site, Land Department inspection photo 1, 24 February 2025
  • Clearpoint construction site, Land Department inspection photo 2, 24 February 2025
  • Clearpoint construction site, Land Department inspection photo 3, 24 February 2025
  • Clearpoint construction site, Land Department inspection photo 4, 24 February 2025

7 November 2024

5.6%+4.2 pts

  • Clearpoint construction site, Land Department inspection photo 1, 7 November 2024
  • Clearpoint construction site, Land Department inspection photo 2, 7 November 2024
  • Clearpoint construction site, Land Department inspection photo 3, 7 November 2024
  • Clearpoint construction site, Land Department inspection photo 4, 7 November 2024

10 May 2024

1.4%+1.4 pts

  • Clearpoint construction site, Land Department inspection photo 1, 10 May 2024
  • Clearpoint construction site, Land Department inspection photo 2, 10 May 2024
  • Clearpoint construction site, Land Department inspection photo 3, 10 May 2024
  • Clearpoint construction site, Land Department inspection photo 4, 10 May 2024

8 August 2023

0%

  • Clearpoint construction site, Land Department inspection photo 1, 8 August 2023
  • Clearpoint construction site, Land Department inspection photo 2, 8 August 2023
  • Clearpoint construction site, Land Department inspection photo 3, 8 August 2023

All 36 site photos, by inspection date

Context

Mina Rashid has 18 projects under construction, 21% built on average.

Mina Rashid Properties has 20 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Clearpoint?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Clearpoint be completed?
The Land Department has no completion date on record for Clearpoint yet.
How much of Clearpoint is built?
45%, measured at the Land Department site inspection on 21 April 2026. The Land Department engineers have inspected the site 7 times since August 2023.
Who is building Clearpoint?
The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Clearpoint?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.