Seascape construction progress
Seascape in Mina Rashid is 79% built at the Land Department inspection of May 2026. Developer Mina Rashid Properties. Completion registered for November 2026.
79%
Built, at the Land Department site inspection of 6 May 2026
On pace for its date
- Completion date (Land Department)
- November 2026
- Finish at recent pace
- December 2026
- Construction started
- April 2023
- Registered with the Land Department
- December 2022
- Developer
- Mina Rashid Properties
- Community
- Mina Rashid
- Units
- 395
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- سي سكيب
- Land Department project number
- 2513
- Land Department site inspections
- 10
Schedule
Since June 2025 Seascape has added about 2.9 points a month. That puts 100% around December 2026, within three months of its registered completion date of November 2026.
Site inspections
6 May 2026
79%+9.7 pts
19 January 2026
69%+4.0 pts
17 November 2025
65%+16 pts
30 June 2025
50%+9.1 pts
9 March 2025
41%+14 pts
18 November 2024
27%+18 pts
1 May 2024
9.0%+7.1 pts
2 October 2023
1.9%+1.9 pts
5 June 2023
0%+0.0 pts
14 November 2022
0%
Context
Mina Rashid has 18 projects under construction, 21% built on average.
Mina Rashid Properties has 20 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Seascape?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Seascape be completed?
- The completion date registered with the Dubai Land Department is November 2026. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Seascape is built?
- 79%, measured at the Land Department site inspection on 6 May 2026. The Land Department engineers have inspected the site 10 times since November 2022.
- Is Seascape delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2026.
- Who is building Seascape?
- The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
- Which bank holds the escrow account for Seascape?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- ClearpointAlso by Mina Rashid Properties. 45%.
- BaylineAlso by Mina Rashid Properties. 61%.
- AvonleaAlso by Mina Rashid Properties. 64%.
- Ocean PointAlso by Mina Rashid Properties. 27%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)