Porto View construction progress
The registered completion date for Porto View in Mina Rashid is October 2028. At the last site inspection, in June 2026, it was 6.3% built. The developer is Mina Rashid Properties.
6.3%
Built, at the site inspection of 2 June 2026
Running behind its date
- Registered completion date
- October 2028
- Finish at recent pace
- September 2039
- Construction started
- February 2025
- First registered
- September 2024
- Developer
- Mina Rashid Properties
- Community
- Mina Rashid
- Units
- 115
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بورتو فيو
- Project number
- 3306
- Site inspections
- 4
Schedule
Between July 2025 and June 2026 the site added about 0.6 points a month. At that rate it would finish around September 2039, more than three months after its registered date of October 2028.
Site inspections
2 June 2026
6.3%+0.4 pts
7 January 2026
5.8%+5.7 pts
21 July 2025
0.1%+0.1 pts
19 September 2024
0%
Context
Mina Rashid has 18 projects under construction, 21% built on average.
Mina Rashid Properties has 20 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Porto View?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Porto View handover date?
- The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Porto View?
- Porto View was 6.3% built at the site inspection on 2 June 2026. The site has been inspected 4 times since September 2024. The Land Department took 15 site photos at its inspections.
- Is Porto View delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Porto View?
- The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
- Which bank holds the escrow account for Porto View?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SeascapeAlso by Mina Rashid Properties. 79%, Due November 2026.
- ClearpointAlso by Mina Rashid Properties. 45%.
- BaylineAlso by Mina Rashid Properties. 61%.
- AvonleaAlso by Mina Rashid Properties. 64%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.



.jpeg&w=3840&q=75)