Ocean Star construction progress
Ocean Star in Mina Rashid was registered to complete in July 2025 and is still under construction. At the last site inspection, in August 2026, it was 30% built. The developer is Mina Rashid Properties.
30%
Built, at the site inspection of 11 August 2026
16 months past its registered completion date
- Registered completion date
- July 2025
- Finish at recent pace
- September 2028
- Construction started
- July 2024
- First registered
- March 2024
- Developer
- Mina Rashid Properties
- Community
- Mina Rashid
- Units
- 155
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- اوشن ستار
- Project number
- 3010
- Site inspections
- 6
Schedule
Ocean Star was registered to complete in July 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around September 2028.
Site inspections
11 August 2026
30%+10 pts
21 April 2026
20%+12 pts
8 December 2025
8.5%+1.9 pts
23 July 2025
6.7%+1.0 pts
17 April 2025
5.7%+5.7 pts
21 March 2024
0%
Context
Mina Rashid has 18 projects under construction, 21% built on average.
Mina Rashid Properties has 20 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Ocean Star?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ocean Star handover date?
- The registered completion date was July 2025, and the register still lists Ocean Star as under construction. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ocean Star?
- Ocean Star was 30% built at the site inspection on 11 August 2026. The site has been inspected 6 times since March 2024. The Land Department took 32 site photos at its inspections.
- Is Ocean Star delayed?
- Yes. Its registered completion date of July 2025 has passed and the project is still listed as under construction.
- Who is building Ocean Star?
- The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
- Which bank holds the escrow account for Ocean Star?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SeascapeAlso by Mina Rashid Properties. 79%, Due November 2026.
- ClearpointAlso by Mina Rashid Properties. 45%.
- BaylineAlso by Mina Rashid Properties. 61%.
- AvonleaAlso by Mina Rashid Properties. 64%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.