Skip to content

Ocean Cove construction progress

Ocean Cove in Mina Rashid is 18% built at the Land Department inspection of April 2026. Developer Mina Rashid Properties. Completion registered for August 2028.

18%

Built, at the Land Department site inspection of 14 April 2026

Running behind its date

Completion date (Land Department)
August 2028
Finish at recent pace
January 2032
Construction started
October 2024
Registered with the Land Department
July 2024
Community
Mina Rashid
Units
233
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
أوشن كوف
Land Department project number
3173
Land Department site inspections
4

Schedule

Between May 2025 and April 2026 the site added about 1.2 points a month. At that rate it would finish around January 2032, more than three months after the August 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 April 2026

18%+8.4 pts

  • Ocean Cove construction site, Land Department inspection photo 1, 14 April 2026
  • Ocean Cove construction site, Land Department inspection photo 2, 14 April 2026
  • Ocean Cove construction site, Land Department inspection photo 3, 14 April 2026
  • Ocean Cove construction site, Land Department inspection photo 4, 14 April 2026

8 December 2025

9.6%+4.4 pts

  • Ocean Cove construction site, Land Department inspection photo 1, 8 December 2025
  • Ocean Cove construction site, Land Department inspection photo 2, 8 December 2025
  • Ocean Cove construction site, Land Department inspection photo 3, 8 December 2025
  • Ocean Cove construction site, Land Department inspection photo 4, 8 December 2025

22 May 2025

5.2%+5.2 pts

  • Ocean Cove construction site, Land Department inspection photo 1, 22 May 2025
  • Ocean Cove construction site, Land Department inspection photo 2, 22 May 2025
  • Ocean Cove construction site, Land Department inspection photo 3, 22 May 2025

2 July 2024

0%

  • Ocean Cove construction site, Land Department inspection photo 1, 2 July 2024
  • Ocean Cove construction site, Land Department inspection photo 2, 2 July 2024

All 18 site photos, by inspection date

Context

Mina Rashid has 18 projects under construction, 21% built on average.

Mina Rashid Properties has 20 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Ocean Cove?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Ocean Cove be completed?
The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around January 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ocean Cove is built?
18%, measured at the Land Department site inspection on 14 April 2026. The Land Department engineers have inspected the site 4 times since July 2024.
Is Ocean Cove delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building Ocean Cove?
The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Ocean Cove?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.