Skip to content

Ocean Cove construction progress

The registered completion date for Ocean Cove in Mina Rashid is August 2028. At the last site inspection, in April 2026, it was 18% built. The developer is Mina Rashid Properties.

18%

Built, at the site inspection of 14 April 2026

Running behind its date

Registered completion date
August 2028
Finish at recent pace
January 2032
Construction started
October 2024
First registered
July 2024
Community
Mina Rashid
Units
233
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
أوشن كوف
Project number
3173
Site inspections
4

Schedule

Between May 2025 and April 2026 the site added about 1.2 points a month. At that rate it would finish around January 2032, more than three months after its registered date of August 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 April 2026

18%+8.4 pts

  • Ocean Cove construction site, inspection photo 1, 14 April 2026
  • Ocean Cove construction site, inspection photo 2, 14 April 2026
  • Ocean Cove construction site, inspection photo 3, 14 April 2026
  • Ocean Cove construction site, inspection photo 4, 14 April 2026

8 December 2025

9.6%+4.4 pts

  • Ocean Cove construction site, inspection photo 1, 8 December 2025
  • Ocean Cove construction site, inspection photo 2, 8 December 2025
  • Ocean Cove construction site, inspection photo 3, 8 December 2025
  • Ocean Cove construction site, inspection photo 4, 8 December 2025

22 May 2025

5.2%+5.2 pts

  • Ocean Cove construction site, inspection photo 1, 22 May 2025
  • Ocean Cove construction site, inspection photo 2, 22 May 2025
  • Ocean Cove construction site, inspection photo 3, 22 May 2025

2 July 2024

0%

  • Ocean Cove construction site, inspection photo 1, 2 July 2024
  • Ocean Cove construction site, inspection photo 2, 2 July 2024

All 18 site photos, by inspection date

Context

Mina Rashid has 18 projects under construction, 21% built on average.

Mina Rashid Properties has 20 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Ocean Cove?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ocean Cove handover date?
The registered completion date is August 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ocean Cove?
Ocean Cove was 18% built at the site inspection on 14 April 2026. The site has been inspected 4 times since July 2024. The Land Department took 18 site photos at its inspections.
Is Ocean Cove delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building Ocean Cove?
The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Ocean Cove?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.