Marina Place 1 construction progress
Marina Place 1 in Mina Rashid is 4.2% built at the Land Department inspection of April 2026. Developer Mina Rashid Properties. Completion registered for December 2028.
4.2%
Built, at the Land Department site inspection of 3 April 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- February 2034
- Construction started
- April 2025
- Registered with the Land Department
- November 2024
- Developer
- Mina Rashid Properties
- Community
- Mina Rashid
- Units
- 162
- Escrow bank
- Emirates NBD
- Name in Arabic
- مارينا بلايس 1
- Land Department project number
- 3386
- Land Department site inspections
- 3
Schedule
Between December 2025 and April 2026 the site added about 1.0 points a month. At that rate it would finish around February 2034, more than three months after the December 2028 date registered with the Land Department.
Site inspections
3 April 2026
4.2%+3.9 pts
8 December 2025
0.4%+0.4 pts
5 November 2024
0%
Context
Mina Rashid has 18 projects under construction, 21% built on average.
Mina Rashid Properties has 20 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Marina Place 1?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Marina Place 1 be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around February 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Marina Place 1 is built?
- 4.2%, measured at the Land Department site inspection on 3 April 2026. The Land Department engineers have inspected the site 3 times since November 2024.
- Is Marina Place 1 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Marina Place 1?
- The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
- Which bank holds the escrow account for Marina Place 1?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SeascapeAlso by Mina Rashid Properties. 79%, Due November 2026.
- ClearpointAlso by Mina Rashid Properties. 45%.
- BaylineAlso by Mina Rashid Properties. 61%.
- AvonleaAlso by Mina Rashid Properties. 64%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)





.jpg&w=3840&q=75)