Marina Place 1 construction progress

Marina Place 1 in Mina Rashid is 4.2% built at the Land Department inspection of April 2026. Developer Mina Rashid Properties. Completion registered for December 2028.

4.2%

Built, at the Land Department site inspection of 3 April 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
February 2034
Construction started
April 2025
Registered with the Land Department
November 2024
Community
Mina Rashid
Units
162
Escrow bank
Emirates NBD
Name in Arabic
مارينا بلايس 1
Land Department project number
3386
Land Department site inspections
3

Schedule

Between December 2025 and April 2026 the site added about 1.0 points a month. At that rate it would finish around February 2034, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 April 2026

4.2%+3.9 pts

  • Marina Place 1 construction site, Land Department inspection photo 1, 3 April 2026
  • Marina Place 1 construction site, Land Department inspection photo 2, 3 April 2026
  • Marina Place 1 construction site, Land Department inspection photo 3, 3 April 2026
  • Marina Place 1 construction site, Land Department inspection photo 4, 3 April 2026

8 December 2025

0.4%+0.4 pts

  • Marina Place 1 construction site, Land Department inspection photo 1, 8 December 2025
  • Marina Place 1 construction site, Land Department inspection photo 2, 8 December 2025
  • Marina Place 1 construction site, Land Department inspection photo 3, 8 December 2025
  • Marina Place 1 construction site, Land Department inspection photo 4, 8 December 2025

5 November 2024

0%

  • Marina Place 1 construction site, Land Department inspection photo 1, 5 November 2024
  • Marina Place 1 construction site, Land Department inspection photo 2, 5 November 2024

All 12 site photos, by inspection date

Context

Mina Rashid has 18 projects under construction, 21% built on average.

Mina Rashid Properties has 20 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Marina Place 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Marina Place 1 be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around February 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Marina Place 1 is built?
4.2%, measured at the Land Department site inspection on 3 April 2026. The Land Department engineers have inspected the site 3 times since November 2024.
Is Marina Place 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Marina Place 1?
The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Marina Place 1?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.