Skip to content

Clearpoint construction photos

36 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Clearpoint was built on the day of each visit.

21 April 202645% built

24 November 202532% built

3 July 202519% built

24 February 202510% built

7 November 20245.6% built

10 May 20241.4% built

8 August 20230% built

Back to Clearpoint construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.