Baystar By Vida construction progress

The registered completion date for Baystar By Vida in Mina Rashid is December 2029. At the last site inspection, in June 2026, it was 6.3% built. The developer is Mina Rashid Properties.

6.3%

Built, at the site inspection of 16 June 2026

Running behind its date

Registered completion date
December 2029
Finish at recent pace
November 2039
Construction started
December 2025
First registered
July 2025
Community
Mina Rashid
Units
328
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
باي ستار من فيدا
Project number
4002
Site inspections
3

Schedule

Between July 2025 and June 2026 the site added about 0.6 points a month. At that rate it would finish around November 2039, more than three months after its registered date of December 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 June 2026

6.3%+5.9 pts

  • Baystar By Vida construction site, inspection photo 1, 16 June 2026
  • Baystar By Vida construction site, inspection photo 2, 16 June 2026
  • Baystar By Vida construction site, inspection photo 3, 16 June 2026
  • Baystar By Vida construction site, inspection photo 4, 16 June 2026

19 February 2026

0.4%+0.4 pts

  • Baystar By Vida construction site, inspection photo 1, 19 February 2026
  • Baystar By Vida construction site, inspection photo 2, 19 February 2026
  • Baystar By Vida construction site, inspection photo 3, 19 February 2026

22 July 2025

0%

  • Baystar By Vida construction site, inspection photo 1, 22 July 2025

All 10 site photos, by inspection date

Context

Mina Rashid has 18 projects under construction, 21% built on average.

Mina Rashid Properties has 20 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Baystar By Vida?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Baystar By Vida handover date?
The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Baystar By Vida?
Baystar By Vida was 6.3% built at the site inspection on 16 June 2026. The site has been inspected 3 times since July 2025. The Land Department took 10 site photos at its inspections.
Is Baystar By Vida delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Baystar By Vida?
The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Baystar By Vida?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.