Baystar By Vida construction progress

Baystar By Vida in Mina Rashid is 6.3% built at the Land Department inspection of June 2026. Developer Mina Rashid Properties. Completion registered for December 2029.

6.3%

Built, at the Land Department site inspection of 16 June 2026

Running behind its date

Completion date (Land Department)
December 2029
Finish at recent pace
November 2039
Construction started
December 2025
Registered with the Land Department
July 2025
Community
Mina Rashid
Units
328
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
باي ستار من فيدا
Land Department project number
4002
Land Department site inspections
3

Schedule

Between July 2025 and June 2026 the site added about 0.6 points a month. At that rate it would finish around November 2039, more than three months after the December 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 June 2026

6.3%+5.9 pts

  • Baystar By Vida construction site, Land Department inspection photo 1, 16 June 2026
  • Baystar By Vida construction site, Land Department inspection photo 2, 16 June 2026
  • Baystar By Vida construction site, Land Department inspection photo 3, 16 June 2026
  • Baystar By Vida construction site, Land Department inspection photo 4, 16 June 2026

19 February 2026

0.4%+0.4 pts

  • Baystar By Vida construction site, Land Department inspection photo 1, 19 February 2026
  • Baystar By Vida construction site, Land Department inspection photo 2, 19 February 2026
  • Baystar By Vida construction site, Land Department inspection photo 3, 19 February 2026

22 July 2025

0%

  • Baystar By Vida construction site, Land Department inspection photo 1, 22 July 2025

All 10 site photos, by inspection date

Context

Mina Rashid has 18 projects under construction, 21% built on average. Baystar By Vida is behind that average.

Mina Rashid Properties has 20 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Baystar By Vida?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Baystar By Vida be completed?
The completion date registered with the Dubai Land Department is December 2029. At the pace of its recent inspections the site would reach 100% around November 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Baystar By Vida is built?
6.3%, measured at the Land Department site inspection on 16 June 2026. The Land Department engineers have inspected the site 3 times since July 2025.
Is Baystar By Vida delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Baystar By Vida?
The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Baystar By Vida?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.