Aurea construction progress

Aurea in Mina Rashid is 0.2% built at the Land Department inspection of October 2026. Developer Mina Rashid Properties. Completion registered for June 2030.

0.2%

Built, at the Land Department site inspection of 2 October 2026

Running behind its date

Completion date (Land Department)
June 2030
Finish at recent pace
March 2491
Construction started
March 2026
Registered with the Land Department
September 2025
Community
Mina Rashid
Units
172
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
اوريا
Land Department project number
4115
Land Department site inspections
2

Schedule

Between September 2025 and October 2026 the site added about 0.0 points a month. At that rate it would finish around March 2491, more than three months after the June 2030 date registered with the Land Department.

0%25%50%75%100%20262027202820292030
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

2 October 2026

0.2%+0.2 pts

  • Aurea construction site, Land Department inspection photo 1, 2 October 2026
  • Aurea construction site, Land Department inspection photo 2, 2 October 2026
  • Aurea construction site, Land Department inspection photo 3, 2 October 2026
  • Aurea construction site, Land Department inspection photo 4, 2 October 2026

23 September 2025

0%

  • Aurea construction site, Land Department inspection photo 1, 23 September 2025
  • Aurea construction site, Land Department inspection photo 2, 23 September 2025

All 6 site photos, by inspection date

Context

Mina Rashid has 18 projects under construction, 21% built on average.

Mina Rashid Properties has 20 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Aurea?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Aurea be completed?
The completion date registered with the Dubai Land Department is June 2030. At the pace of its recent inspections the site would reach 100% around March 2491. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Aurea is built?
0.2%, measured at the Land Department site inspection on 2 October 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Aurea delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2030.
Who is building Aurea?
The registered developer is Mina Rashid Properties. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Aurea?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.