Qpoint Liwan-Plot R100 construction progress

The register lists Qpoint Liwan-Plot R100 in Liwan1 as complete, with a registered completion date of June 2014. Its last site inspection on record was in May 2014. The developer is Al Mazaya Real Estate.

100%

Built, at the site inspection of 19 May 2014

Construction complete

Registered completion date
June 2014
Construction started
June 2009
First registered
June 2009
Developer
Al Mazaya Real Estate
Community
Liwan1
Units
40
Escrow bank
Mashreq Bank
Name in Arabic
كيو بوينت ليوان -Plot R100
Project number
1232
Site inspections
6

Schedule

The register lists Qpoint Liwan-Plot R100 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20102011201220132014
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 May 2014

92%+8.7 pts

  • Qpoint Liwan-Plot R100 construction site, inspection photo 1, 19 May 2014
  • Qpoint Liwan-Plot R100 construction site, inspection photo 2, 19 May 2014
  • Qpoint Liwan-Plot R100 construction site, inspection photo 3, 19 May 2014
  • Qpoint Liwan-Plot R100 construction site, inspection photo 4, 19 May 2014

3 February 2014

83%+6.3 pts

  • Qpoint Liwan-Plot R100 construction site, inspection photo 1, 3 February 2014
  • Qpoint Liwan-Plot R100 construction site, inspection photo 2, 3 February 2014
  • Qpoint Liwan-Plot R100 construction site, inspection photo 3, 3 February 2014
  • Qpoint Liwan-Plot R100 construction site, inspection photo 4, 3 February 2014

15 September 2013

77%+0.5 pts

  • Qpoint Liwan-Plot R100 construction site, inspection photo 1, 15 September 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 2, 15 September 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 3, 15 September 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 4, 15 September 2013

3 June 2013

76%+5.5 pts

  • Qpoint Liwan-Plot R100 construction site, inspection photo 1, 3 June 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 2, 3 June 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 3, 3 June 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 4, 3 June 2013

11 February 2013

71%

  • Qpoint Liwan-Plot R100 construction site, inspection photo 1, 11 February 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 2, 11 February 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 3, 11 February 2013
  • Qpoint Liwan-Plot R100 construction site, inspection photo 4, 11 February 2013

2 October 2012

71%

  • Qpoint Liwan-Plot R100 construction site, inspection photo 1, 2 October 2012
  • Qpoint Liwan-Plot R100 construction site, inspection photo 2, 2 October 2012
  • Qpoint Liwan-Plot R100 construction site, inspection photo 3, 2 October 2012
  • Qpoint Liwan-Plot R100 construction site, inspection photo 4, 2 October 2012

All 52 site photos, by inspection date

Context

Liwan1 has 6 projects under construction, 28% built on average.

Own a unit in Qpoint Liwan-Plot R100?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Qpoint Liwan-Plot R100 handover date?
Construction of Qpoint Liwan-Plot R100 is recorded as complete, with a registered completion date of June 2014. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Qpoint Liwan-Plot R100?
Qpoint Liwan-Plot R100 was 100% built at the site inspection on 19 May 2014. The site has been inspected 6 times since October 2012. The Land Department took 52 site photos at its inspections.
Is Qpoint Liwan-Plot R100 delayed?
The register lists construction as complete.
Who is building Qpoint Liwan-Plot R100?
The registered developer is Al Mazaya Real Estate.
Which bank holds the escrow account for Qpoint Liwan-Plot R100?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.