Qpoint Liwan-Plot R096 construction progress

The register lists Qpoint Liwan-Plot R096 in Liwan1 as complete, with a registered completion date of August 2015. Its last site inspection on record was in April 2015. The developer is Al Mazaya Holding.

100%

Built, at the site inspection of 20 April 2015

Construction complete

Registered completion date
August 2015
Construction started
March 2009
First registered
June 2009
Developer
Al Mazaya Holding
Community
Liwan1
Units
55
Escrow bank
Mashreq Bank
Name in Arabic
كيو بوينت ليوان -Plot R096
Project number
1214
Site inspections
9

Schedule

The register lists Qpoint Liwan-Plot R096 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201020122014
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 April 2015

68%+4.2 pts

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 20 April 2015
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 20 April 2015
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 20 April 2015
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 20 April 2015

14 December 2014

64%+14 pts

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 14 December 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 14 December 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 14 December 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 14 December 2014

31 August 2014

50%+4.4 pts

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 31 August 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 31 August 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 31 August 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 31 August 2014

19 May 2014

46%+0.1 pts

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 19 May 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 19 May 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 19 May 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 19 May 2014

17 March 2014

46%+9.3 pts

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 17 March 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 17 March 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 17 March 2014
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 17 March 2014

6 August 2013

36%+16 pts

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 6 August 2013
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 6 August 2013
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 6 August 2013
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 6 August 2013

3 April 2013

20%+8.0 pts

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 3 April 2013
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 3 April 2013
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 3 April 2013
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 3 April 2013

9 September 2012

12%+3.5 pts

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 9 September 2012
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 9 September 2012
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 9 September 2012
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 9 September 2012

22 May 2012

8.5%

  • Qpoint Liwan-Plot R096 construction site, inspection photo 1, 22 May 2012
  • Qpoint Liwan-Plot R096 construction site, inspection photo 2, 22 May 2012
  • Qpoint Liwan-Plot R096 construction site, inspection photo 3, 22 May 2012
  • Qpoint Liwan-Plot R096 construction site, inspection photo 4, 22 May 2012

All 59 site photos, by inspection date

Context

Liwan1 has 6 projects under construction, 28% built on average.

Al Mazaya Holding has 1 project under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Qpoint Liwan-Plot R096?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Qpoint Liwan-Plot R096 handover date?
Construction of Qpoint Liwan-Plot R096 is recorded as complete, with a registered completion date of August 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Qpoint Liwan-Plot R096?
Qpoint Liwan-Plot R096 was 100% built at the site inspection on 20 April 2015. The site has been inspected 9 times since May 2012. The Land Department took 59 site photos at its inspections.
Is Qpoint Liwan-Plot R096 delayed?
The register lists construction as complete.
Who is building Qpoint Liwan-Plot R096?
The registered developer is Al Mazaya Holding. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Qpoint Liwan-Plot R096?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.