Skip to content

Qpoint Liwan-Plot R005 construction progress

The register lists Qpoint Liwan-Plot R005 in Liwan1 as complete, with a registered completion date of May 2014. Its last site inspection on record was in April 2014. The developer is Al Mazaya Real Estate.

100%

Built, at the site inspection of 7 April 2014

Construction complete

Registered completion date
May 2014
Construction started
December 2008
First registered
June 2009
Developer
Al Mazaya Real Estate
Community
Liwan1
Units
217
Escrow bank
Mashreq Bank
Name in Arabic
كيو بوينت ليوان -Plot R005
Project number
1189
Site inspections
5

Schedule

The register lists Qpoint Liwan-Plot R005 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%200920112013
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 April 2014

99%+3.4 pts

  • Qpoint Liwan-Plot R005 construction site, inspection photo 1, 7 April 2014
  • Qpoint Liwan-Plot R005 construction site, inspection photo 2, 7 April 2014
  • Qpoint Liwan-Plot R005 construction site, inspection photo 3, 7 April 2014
  • Qpoint Liwan-Plot R005 construction site, inspection photo 4, 7 April 2014

18 August 2013

96%+3.3 pts

  • Qpoint Liwan-Plot R005 construction site, inspection photo 1, 18 August 2013

3 April 2013

92%+1.3 pts

  • Qpoint Liwan-Plot R005 construction site, inspection photo 1, 3 April 2013
  • Qpoint Liwan-Plot R005 construction site, inspection photo 2, 3 April 2013
  • Qpoint Liwan-Plot R005 construction site, inspection photo 3, 3 April 2013
  • Qpoint Liwan-Plot R005 construction site, inspection photo 4, 3 April 2013

15 October 2012

91%+5.0 pts

  • Qpoint Liwan-Plot R005 construction site, inspection photo 1, 15 October 2012
  • Qpoint Liwan-Plot R005 construction site, inspection photo 2, 15 October 2012
  • Qpoint Liwan-Plot R005 construction site, inspection photo 3, 15 October 2012
  • Qpoint Liwan-Plot R005 construction site, inspection photo 4, 15 October 2012

20 June 2012

86%

  • Qpoint Liwan-Plot R005 construction site, inspection photo 1, 20 June 2012
  • Qpoint Liwan-Plot R005 construction site, inspection photo 2, 20 June 2012
  • Qpoint Liwan-Plot R005 construction site, inspection photo 3, 20 June 2012
  • Qpoint Liwan-Plot R005 construction site, inspection photo 4, 20 June 2012

All 45 site photos, by inspection date

Context

Liwan1 has 6 projects under construction, 28% built on average.

Own a unit in Qpoint Liwan-Plot R005?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Qpoint Liwan-Plot R005 handover date?
Construction of Qpoint Liwan-Plot R005 is recorded as complete, with a registered completion date of May 2014. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Qpoint Liwan-Plot R005?
Qpoint Liwan-Plot R005 was 100% built at the site inspection on 7 April 2014. The site has been inspected 5 times since June 2012. The Land Department took 45 site photos at its inspections.
Is Qpoint Liwan-Plot R005 delayed?
The register lists construction as complete.
Who is building Qpoint Liwan-Plot R005?
The registered developer is Al Mazaya Real Estate.
Which bank holds the escrow account for Qpoint Liwan-Plot R005?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.